Northwestern Water and Sewer District Projects – May 14

Northwestern Water and Sewer District Projects

BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties.  Although many of our construction and maintenance projects are performed underground, our utility work can impact roads throughout our service area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined.

Middleton and Plain Townships – Potter Road Waterline Installation
Through May, restoration and pavement work will continue on Potter Road from Poe Road to Long-Judson Road with minimal impact to traffic.  Project complete: May.

Millbury – Sanitary Sewer Improvements
Through June, short-term, intermittent lane restrictions are possible throughout the Village of Millbury for sewer work and manhole repairs.  Project complete: June.

Perrysburg Township – Hamlet Waterline Replacement
Through June, short-term intermittent lane restrictions and closures are possible in the Hamlet subdivision for waterline installation and restoration work.  Local access will be maintained.  Project complete: August.

Perrysburg Township – Sanitary Sewer Improvements
Through October, short-term intermittent lane restrictions are possible throughout Perrysburg Township, north of SR 795, for sewer work and manhole repair.  Project complete: October.

Rossford & Perrysburg Township – Waterline Replacement *NEW PROJECT*
Effective today through August, intermittent lane restrictions are possible on Vineyard and Groce Streets in Rossford and on Riverbend Court and White Street in Perrysburg Township for waterline replacement.  The one day closure of Superior Street at White Street will be announced.  Project complete: August.

Rossford – Buck and Lime City Road Water Line Relocation and Improvements 
Through May, short-term, intermittent lane restrictions are possible on Buck Road between I-75 and Lime City Road and on Lime City Road between I -75 and Marilyn Drive for restoration work.  Project complete: May. 

Weston – Waterline Project 
Through May, short-term intermittent lane restrictions are possible on Silver Street between Sugar Lane and Euler Street for restoration. Project complete: June.

Weston – Pump Station Project
Through May, intermittent, short-term lane restrictions are possible on Main Street, between Russ Street and Weston Road for restorations.  Project complete:  May.

OTHER PROJECTS

Liberty Township – Bulk Water Station Closure
Through May, The District Bulk Water station at Bays Road near I-75 is closed for water tower painting.  For alternative Bulk Water Stations, click here.

Smoke Testing  McComb
Effective Tuesday, May 15, through Friday, May 25, District crews will be smoke testing sewer system in the Village of McComb.  Crews will be using non-toxic smoke in the sewer system to identify potential defects and cross-connections to the storm sewer system.

Hydrant Flushing
Through June, weekdays from 8 am until 3:30 pm, crews will be flushing and testing fire hydrants in southern Wood County and in McComb in Hancock County.  Residents are advised to flush water from their taps if the water becomes discolored.  For more information: http://www.nwwsd.org/what-we-do/water/water-facts/hydrant-main-line-flushing-info/

For a full list of projects on and off road, please visit our website:
http://www.nwwsd.org/working-with-us/projects/