BOWLING GREEN (Tuesday, December 06, 2016) – The Ohio Department of Transportation (ODOT) District Two announces the following updates to the I-75 widening project in Wood and Hancock Counties. Updates are highlighted in bold and underlined:

Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions:  Through December, overnight, from 7pm until 6am, single lane restrictions are possible on I-75, between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.  Through July 2017, single lane restrictions are possible on I-75, between US 20 and CR 99 in Hancock County, for finish work.

Effective Wednesday, December 7, from 10am until 6pm, single lane restrictions are possible on northbound I-75, between US 224 and Eagleville Road, for traffic pattern change.

Effective Thursday, December 8, from 9am until 4pm, single lane restrictions are possible on southbound I-75, between US 20 and I-475, for sign installation.

Southbound I-75, between Roachton Road and Eagleville Road, is now open to three lanes.

Northbound I-75, between Eagleville Road and SR 582, is now open to three lanes.

Ramp Restrictions:

Effective Wednesday, December 7, from 8:30am until 1pm, short-term ramp closures are possible on the following ramps for striping.  Two consecutive exits will not be closed at the same time.

·         The ramps to/from northbound I-75 to/from Eagleville Road (Exit 168).

·         The ramps to/from northbound I-75 to/from SR 18 (Exit 167).

·         The ramps to/from northbound I-75 to/from SR 613 (Exit 164).

·         The ramps to/from northbound I-75 to/from CR 99 (Exit 161).

Project complete: October 2017.  All work is weather permitting.