I-75 widening project in Wood and Hancock Counties

 

Ohio Department of Transportation  •  Traffic Advisory

District 2  • Todd M. Audet, P.E., Deputy Director
317 East Poe Rd. • Bowling Green, Ohio 43402-1330
www.transportation.ohio.gov/dist2

Interstate 75 Widening in Wood and Hancock Counties 

BOWLING GREEN (Tuesday, March 22, 2016) – The Ohio Department of Transportation (ODOT) District Two announces the following update to the I-75 widening project in Wood and Hancock Counties. Updates are highlighted in bold and underlined:

Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions:
Effective Saturday, March 19, from 5am until 10am, southbound I-75, between Oil Center Road and SR 18, may be reduced to one lane for barrier repair.

Effective tonight at 7pm, through Wednesday, March 23 at 6am, northbound I-75, between US 224 and CR 101, may be reduced to one lane for pavement shift.

Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.  Through December, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through December, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.

Ramp Restrictions:

·         Through July, 11-foot lane width restrictions are in place on the ramps from northbound and southbound I-75 to Cygnet Road (Exit 171) and from Cygnet Road to northbound and southbound I-75.

·         Through October, southbound I-75 to westbound I-475 is reduced to one 11-foot lane for pavement installation.

Local Routes:
Through March, Bays Road at I-75 is closed for bridge work.  Detour: SR 25; SR 281; Solether Road.

Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75.

Project complete: October 2017.  All work is weather permitting.