Northwestern Water and Sewer District Projects – Oct. 15
BOWLING GREEN, Ohio, – Northwestern Water and Sewer District Projects – Oct. 15 The District will announce updates and when additional projects are under contract. Updates and additions are highlighted in bold and underlined.
Perrysburg Township – Starbright Subdivision Waterline Replacement *UPDATE*
Through October, short-term, intermittent lane restrictions are possible throughout the Starbright subdivision for restoration work.
Perrysburg Township – Sanitary Sewer Improvements
Through November, short-term intermittent lane restrictions are possible throughout Perrysburg Township for sewer work and manhole repair. Project complete: November.
Rossford & Perrysburg Township – Waterline Replacement *UPDATE*
Through November, intermittent lane restrictions are possible on Vineyard and Groce Streets in Rossford and on Riverbend Court and White Road in Perrysburg Township for waterline replacement. Restoration work will take place in the spring. Project complete: November.
Weston – Waterline Replacement
Through December, lane restrictions are possible on Center Street from Main Street to Euler Road and on Euler Road, between Center Street and Silver Street for waterline replacement. Waterline work on Cygnet Road in Cygnet will be announced. Project complete: December.
OTHER PROJECTS
Hydrant Flushing *UPDATE*
Through November, weekdays from 8 am until 3:30 pm, crews will be flushing and testing fire hydrants in Perrysburg Township and Rossford. Residents are advised to flush water from their taps if the water becomes discolored. For more information: http://www.nwwsd.org/what-we-do/water/water-facts/hydrant-main-line-flushing-info/
For a full list of projects on and off road, please visit our website:
http://www.nwwsd.org/working-with-us/projects/