BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact roads throughout our service area. The District will announce updates and when additional projects are under contract. Updates and additions are highlighted in bold and underlined.
Perrysburg Township – Sanitary Sewer Improvements
Through
May, short-term intermittent lane restrictions are possible throughout
Perrysburg Township for sewer work and manhole repair. Project
complete: May.
Rossford & Perrysburg Township – Waterline Replacement
Through
December, intermittent lane restrictions are possible on Vineyard and
Groce Streets in Rossford and on Riverbend Court and White Road in
Perrysburg Township for waterline replacement. Restoration work will
take place in the spring. Project complete: December.
Rossford – Lead Service Line Removal Project *UPDATE*
Effective the week of December 17, through
May, intermittent lane restrictions are possible in Rossford for lead
service line removal. Project complete: May. For more information and
to sign up for email updates go to: https://www.nwwsd.org/what-we-do/water/water-facts/lead/
Weston & Cygnet – Waterline Replacement *PROJECT COMPLETE*
Waterline replacement work in Weston and in Cygnet is now complete. Restoration will be completed in the spring. Project complete: December.