NW Water and Sewer Projects Update

BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties.  Although many of our projects are performed underground, our utility work can impact roads throughout our service area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined.

Perrysburg Township – Sanitary Sewer Improvements
Through May, short-term intermittent lane restrictions are possible throughout Perrysburg Township for sewer work and manhole repair.  Project complete: May.

Rossford & Perrysburg Township – Waterline Replacement
Through December, intermittent lane restrictions are possible on Vineyard and Groce Streets in Rossford and on Riverbend Court and White Road in Perrysburg Township for waterline replacement.  Restoration work will take place in the spring.  Project complete: December.

Rossford – Lead Service Line Removal Project *UPDATE*
Effective the week of December 17,
through May, intermittent lane restrictions are possible in Rossford for lead service line removal.  Project complete: May.  For more information and to sign up for email updates go to:  https://www.nwwsd.org/what-we-do/water/water-facts/lead/

Weston & Cygnet – Waterline Replacement *PROJECT COMPLETE*
Waterline replacement work in Weston and in Cygnet is now complete.
  Restoration will be completed in the spring.  Project complete: December.