Northwestern Water and Sewer District Projects
BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact roads throughout our service area. The District will announce updates and when additional projects are under contract. Updates and additions are highlighted in bold and underlined.
McComb – Sewer Line Replacement *UPDATE*
Through March, lane restrictions and short-term closures are possible at the intersection of Bond and Liberty Streets. Project complete: June. Project investment: $490,000
Perrysburg Township – Sanitary Sewer Improvements
Through May, short-term intermittent lane restrictions are possible throughout Perrysburg Township for sewer work and manhole repair. Project complete: May. Project investment: $998,000.
Lake Township – Waterline & Sewer Installation
Through September, watch for shoulder restrictions and additional construction traffic along Tracy Road from SR 795 to Keller Road for sewer installation. Project complete: September. Project investment: $520,000.
Rossford – Lead Service Line Removal Project
Through May, intermittent lane restrictions are possible in Rossford for lead service line removal. Project complete: May. Project investment: $900,000. For more information and to sign up for email updates go to: https://www.nwwsd.org/what-we-do/water/water-facts/lead/
Rossford – Sewer Lining Project
Through June, watch for shoulder restrictions and construction crews on roads north of Eagle Point Road for sewer lining. Project complete: May. Project investment: $767,000.