North Baltimore, Ohio

September 8, 2024 9:54 am

Northwestern Water and Sewer District Projects – Jan. 21

BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 19,000 customers in Wood, Sandusky, and Hancock counties.  Although many of our projects are performed underground, our utility work can impact roads throughout our service area.  The District will announce updates and when additional projects are under contract.  Updates and additions are highlighted in bold and underlined.

Reminder: The District office will be closed Monday, January 21 for Martin Luther King Day.   

Perrysburg Township – Sanitary Sewer Improvements 
Through May, short-term intermittent lane restrictions are possible throughout Perrysburg Township for sewer work and manhole repair.  Project complete: May. Project investment: $998,000.

Lake Township – Waterline & Sewer Installation *NEW PROJECT*
Through September, watch for shoulder restrictions and additional construction traffic along Tracy Road from SR 795 to Keller Road for sewer installation.  Project complete: September.  Project investment: $520,000.

McComb – Sewer Line Replacement 
Through February, lane restrictions and short-term closures are possible at the intersection of Bond and Liberty Streets.  Project complete: June. Project investment: $490,000

Rossford – Lead Service Line Removal Project 
Through May, intermittent lane restrictions are possible in Rossford for lead service line removal.  Project complete: May. Project investment: $900,000.  For more information and to sign up for email updates go to:  https://www.nwwsd.org/what-we-do/water/water-facts/lead/

Rossford – Sewer Lining *NEW PROJECT*
Effective Tuesday January 22, through June, watch for shoulder restrictions and construction crews on roads north of Eagle Point Road for sewer lining. Project complete: May. Project investment: $767,000.