Northwestern Water and Sewer District
November Important Dates
BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District’s (The District) Board of Trustees has rescheduled the dates of the regular board meetings originally for Thursday, November 11 and on Thursday, November 25 to Thursday, November 4 and Thursday, November 18 at 7:30 a.m., at the offices of The District, 12560 Middleton Pike, Bowling Green, Ohio. This change is necessary due to conflicts on Veterans Day and Thanksgiving. Additionally, The District offices will be closed on the following holidays:
- Thursday, November 11, Veterans Day
- Thursday, November 25, Thanksgiving Day
- Friday, November 26, the day after Thanksgiving
For more information go to NWWSD.org.
District Project Update
BOWLING GREEN, Ohio, – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customers in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are performed underground, our utility work can impact water and sewer service in addition to roads throughout our service area.
Center Township: County Home Waterline Replacement Project
Waterline work impacting traffic on County Home Road, north of Kramer Road, has been delayed until further notice. Additional road restrictions will be announced. Project investment: $358,000.
Cygnet and Jerry City: Pump Station Project
Through November, lane, shoulder, and sidewalk restrictions are possible in the Village of Cygnet, along Front Street, Washington Street, and Union Street, and in Jerry City on Main Street and Leffler Street for pump station work. Project complete: December. Project investment: $578,000.
Lake Township: Water Tower
Through August 2022, crews will be constructing a 1.5-million-gallon elevated water tank near Lemoyne Road between Latcha and Hanley Roads. Residents can expect additional construction vehicle traffic and possible shoulder restrictions in this area. Project complete: September 2022. Project investment: $4 million.
Perrysburg: Sewer Rehabilitation Project
Work on the project impacting traffic on southbound West Boundary Street between Front Street and West Sixth Street, and the closure of Indiana Avenue between West Boundary Street and North Ridge Drive is postponed. Updates on closures will be announced. Project complete: January. Project investment: $747,000.
Weston: Sewer Rehabilitation Project *UPDATE*
Through November, crews will be working in various locations in Weston for sewer rehabilitation. Work is expected to have a minimal impact on roads and sewer service. Project complete: November. Project investment: $900,000.
District-Wide Hydrant Flushing *COMPLETE*
Hydrant flushing throughout The District is now complete. Annual flushing will begin next spring.
District-Wide: Valve Maintenance *UPDATE*
Valve maintenance in Walbridge is complete. Additional work will be announced.