ODOT D – 2 Construction Update – May 13

ODOT District Two Weekly Construction Update – May 13

Updates are highlighted in bold and underlined.

Lucas/Wood Counties

1. Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions: Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.  Through December, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through December, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.

Ramp Restrictions:

·         Effective Monday, May 23 through September, the ramp from northbound I-75 to westbound I-475 in Perrysburg will be closed for bridge work.  Detour: SR 795 (Exit 195); southbound I-75.

·         Effective Monday, May 23, through September, the ramp from eastbound I-475 to northbound I-75 in Perrysburg will be closed for bridge work.  Detour: southbound I-75; SR 582 (Exit 187).

·         Through October, southbound I-75 to westbound I-475 is reduced to one 11-foot lane for pavement installation.

·         Through July, 11-foot lane width restrictions are in place on the ramps from northbound and southbound I-75 to Cygnet Road (Exit 171) and from Cygnet Road to northbound and southbound I-75.

Local Routes:
Through May, Bays Road at I-75 is closed for bridge work.  Detour: SR 25; SR 281; Solether Road.

Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75.

Project complete: October 2017.  All work is weather permitting.

2. Interstate 75: Widening
Lucas County (485-14, 536-14):
  Through September 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for bridge work.  Through September, one lane of I-75 traffic is maintained in the current northbound lane and one lane of traffic is relocated to southbound I-75 and separated by barrier wall.

The following ramps are closed:

  • Through July, the ramp from Phillips Avenue to northbound I-75.  Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.
  • Through July, the ramp from southbound I-75 to Phillips Avenue (Exit 206).  Detour: North Expressway Drive (Exit 207); Stickney Avenue; South Expressway Drive.
  • Through September, the ramp from northbound I-75 to Jeep Parkway (Exit 205A).  Detour: Berdan Avenue (Exit 205B); Detroit Avenue.
  • Through September, the ramp from northbound I-75 to Phillips Avenue (Exit 206).  Detour: south Expressway Drive (Exit 207); Stickney Avenue; North Expressway Drive.
  • Through July 2018, the ramp from Jeep Parkway to southbound I-75.  Detour: Berdan Avenue.
  • Through July 2018, the ramp from Willys Parkway to northbound I-75.  Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue.
  • Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A).  Detour: Detroit Avenue (Exit 203B).

Local Streets:

Through May, expect lane restrictions on Berdan Avenue at I-75 and Detroit Avenue at I-75 for bridge work.

Through June, South Expressway Drive is restricted to a single lane between Stickney Avenue and Lagrange Street.

Through July, expect lane restrictions on Phillips Avenue at I-75 for bridge work.

Through September, Jeep Parkway from Central Avenue to Berdan Avenue is closed.  Detour: Central Avenue; Detroit Avenue; Berdan Avenue.

Through September, the ramp from northbound I-75 to Berdan Avenue is restricted to right turn only movements.  Suggested alternate route: Berdan Avenue; Detroit Avenue; Phillips Avenue; Haverhill Drive.

Through November, Elm Street and Wersell Avenue at South Expressway Drive, is closed.

Through May 2017, the Polish Village Overpass is closed for bridge work.  Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive.

Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed.

Project complete: September 2018.  All work is weather permitting.

3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14): 
Through August, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes.  Overnight, 10pm through 6am, single lane restrictions are possible in this work zone.  Through May, Oakwood Avenue, between Wells Street and Grove Place, is closed for bridge work.  Seek alternate route.

Ramps restrictions and closures:

·         Tonight at 10pm, through Friday, May 13 at 5am, the ramp from Lawrence Avenue to southbound I-75 will be closed for bridge work.  Detour: Monroe Street; Michigan Street.

·         Through May, the ramp from northbound I-75 to Detroit Avenue (Exit 203B) is closed.  Detour: Berdan Avenue (Exit 205B); Detroit Avenue.

·         Through June, the ramp from southbound I-75 to Detroit Avenue (Exit 203B) will be closed.  Detour: Washington Street/Downtown (Exit 202A); 11th Street; Monroe Street.

·         Through August, the interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.

·         Through August, the interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.

·         Through August, the ramp from D­etroit Avenue to southbound I-75 is closed.  Detour: Monroe Street; Michigan Avenue; SR 25.

·         Through August, the ramp from Detroit Avenue to northbound I-75 is closed.  Detour: Monroe Street; 14th Street.

Project complete: August.  All work is weather permitting.

 

4. Interstate 75/280: Rerouting

Lucas County (536-14):  Through June, single lane restrictions are possible on I-280, between Manhattan Boulevard and Central Avenue, for ramp construction.  Through December, Central Avenue, between Buckeye Street and Galena Street, is closed.  Detour: Lagrange Street; Greenbelt Parkway; Galena Street.  Pedestrian access will be maintained.  The northbound I-75 rerouting is expected to begin in May and continue through December.  All work is weather permitting.

 

5. Interstate 75: Pavement Repair *NEW WORK*

Lucas County:  Effective Monday, May 16, through Thursday, May 19, nightly from 9pm until 5am, lane restrictions are possible on the ramps from I-75 to the Ohio Turnpike (Exit 195) for pavement repair.  All work is weather permitting.

6. Interstate 75: Rest Area Closure

Wood County (170-14)Through July, the northbound and southbound I-75 rest areas are closed as part of the I-75 widening project.  Project complete: July.  All work is weather permitting.

7. Interstate 280: Bridge Deck Repairs

Lucas County (1056-15): Through July, shoulder restrictions are possible on the I-280 Veterans’ Glass City Skyway for bridge deck repairs.  Project complete: August.  All work is weather permitting.

8. Interstate 280: Drainage Project
Lucas and Wood Counties (58-16): 
Through May, I-280, between Navarre Avenue and Wales Road, may be reduced to one lane in each direction, for drainage improvements.  Project complete: June.  All work is weather permitting.

9. Interstate 475: ProMedica Parkway Ramp
Lucas County:
  Through December, the ramp from ProMedica Parkway to eastbound I-475 is closed for traffic control.  Detour: westbound I-475; Douglas Road.  All work is weather permitting.

 

10. Interstate 475: Resurfacing and Bridge Project

Lucas County (58-16):  Through September, 11-foot lane width restrictions are in place on I-475 over Secor Road (Exit 17) for bridge work.  Through September, overnight from 8pm until 6am, single lane restrictions are possible on I-475, between the US 23 interchange and Douglas Road, for resurfacing.  Additional restrictions may be announced.  Project complete: October.  All work is weather permitting.

11. Interstate 475/U.S. Route 23: Interchange Upgrade *UPDATE*

Lucas County (184-14):  Effective Friday, May 13 at 9pm, through Saturday, May 14 at 6am, the ramp from westbound I-475 to northbound US 23 will be closed for resurfacing.  Detour: southbound I-475; Central Ave (Exit 13).  Additional ramp closures may be announced.  Through May, southbound US 23 traffic is reduced to one lane from the I-475/US 23 split in Sylvania to Central Avenue. Overnight lane restrictions are possible at the interchange of I-475/US 23 from Central Avenue to N. Holland Sylvania Road.  Project complete: June.  All work is weather permitting.

 

12. Interstate 475: Bridge Widening

Lucas County (235-14):  Through July, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salisbury Road/Dussel Drive for pavement work.  Through August, 11-foot lane width restrictions are in place on I-475, between Angola Road and Salisbury Road/Dussel Drive.  Project complete: August.  All work is weather permitting.

13. Interstate Maintenance Work

Lucas and Wood Counties:  Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work.  Project complete: December.  All work is weather permitting.

14. U.S. Route 20: Central Avenue Interchange Project *UPDATE*
Lucas County (210-15): 
Through September 2017, overnight from 9pm until 6am, lane restrictions are possible on I-475/US 23 between Dorr Street and the I-475/US 23 interchange.  11-foot lane width restrictions are in place within the work zone. Effective Monday, May 16, Plainview Drive at Central Avenue will be permanently closed.  The connector road from Wilford Drive to Plainview Drive will open the week of May 30.  Additional restrictions will be announced.  Project complete: September 2017.  All work is weather permitting. 

 

15. State Route 2: Resurfacing and Bridge Project *UPDATE*
Lucas County (564-15):
  Effective Thursday, June 2, through Sunday, July 3, Airport Highway (SR 2), between Holloway Road and Albon Road, will be closed for bridge repair.  Detour: I-475; Salisbury Road (Exit 6); Briarfield Boulevard; US 20A. Through August, lane restrictions are possible on Airport Highway (SR 2), between Holloway Road and US 20A, for resurfacing.  Additional restrictions and closures will be announced.  Project complete: September.  All work is weather permitting.

16. State Route 2: Intersection Upgrades
Lucas County (142-15): 
Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on SR 2/Airport Highway at Holland Sylvania Road, for intersection upgrades.  Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on SR 2/Airport Highway at Reynolds Road, for intersection upgrades.  Additional restrictions will be announced.  Project Complete: December.  All work is weather permitting.

17. State Route 25: Safety Project *UPDATE*
Lucas County (299-15):
  Through September, southbound (outbound from downtown Toledo)Anthony Wayne Trail, between Hippo Way and City Park Boulevard, is reduced two lanes for pavement rehabilitation.  Additional closures of Western Avenue and South Avenue at the Anthony Wayne Trail will be announced.  Project complete: November.  All work is weather permitting.

 

18. State Route 51: Bridge Repair

Lucas County (60-16):  Through August, Monroe Street/SR 51, between Parkview Avenue and Inwood Drive in Toledo, is reduced to one lane in each direction for bridge repair.  Through June, access to/from Monroe Street to/from Rosedale Avenue, Parkview Avenue, South Cove Boulevard and North Cove Boulevard is maintained through right turn movements only.  Additionally at this time, North Cove Boulevard and South Cove Boulevard, south of Monroe Street, are closed. Suggested alternate route: Upton Avenue.  Additional restrictions or closures will be announced.  Project complete: September.  All work is weather permitting.

 

19. State Route 65: Bridge Deck Repairs

Lucas County (1056-15): Through July, shoulder restrictions are possible on the Robert Craig Memorial Bridge/SR 65 in Toledo for bridge deck repairs.  Additional restrictions may be announced.  Project complete: August.  All work is weather permitting.

20. McCord Road: Underpass Construction
Lucas County (236-14): 
Through September, McCord Road between North Mall Drive/Hall Road and Spectrum Drive is closed to vehicular and pedestrian traffic.  Detour: Holland Park Boulevard; North Mall Drive.  Project complete: November.  All work is weather permitting.

21. Woodley Road: Bridge Repair Project

Lucas County (24-16):  Through October, shoulder restrictions are possible on I-475 at Woodley Road for bridge work.  Through July, Woodley Road, between Ellenridge Lane and Professional Drive, is closed for bridge repair.  Detour: Central Avenue; Talmadge Road; Sylvania Avenue.  Through July, overnight, from 8pm until 6am, single lane restrictions are possible on I-475, between Talmadge Road and Secor Road, for bridge repair.   Project complete: October.  All work is weather permitting.

22. U.S. Route 6: Pavement Reconstruction and Bridge Work
Wood County (170-14):
  Through June, the ramp from southbound I-75 to eastbound US 6 is closed.  Detour: westbound US 6; SR 25.  Through June, US 6, between SR 25 and Dunbridge Road, is reduced to one lane in each direction.  Lane widths are restricted to 11ft in this work zone.  Work complete: June.  All work is weather permitting.

23. State Route 25: Resurfacing *RESTRICTIONS SUNDAY*

Wood County:  Effective Sunday, May 15, from 5am until 7pm, SR 25 over I-475 in Perrysburg will be reduced to one lane in each direction for resurfacing.  All work is weather permitting.

 

24. State Route 51: Culvert Replacements
Wood County (618-15):
  Through May, SR 51, between Frey Road and Mathews Road, is closed for culvert replacement.  Detour: SR 795; I-280.  Additional closures will be announced.  Project complete: September.  All work is weather permitting.

25. State Route 235: Resurfacing
Wood County (441-15): 
Through June, SR 235, between SR 18 and US 6, will be closed for resurfacing.  Detour: SR 18; SR 65; US 6.  Local access will be maintained.  Project Complete: July.  All work is weather permitting.

 

Ottawa/Sandusky/Seneca Counties

 

26. State Route 2: Lightner Road Bridge Widening

Ottawa County (232-15):  Through August, intermittent lane restrictions are possible on SR 2, between SR 53/SE Catawba Road and SR 269, for bridge work.  Additionally, Lightner Road, between Kirk Road and East State Road, may be reduced to one lane for temporary pavement construction.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.
Project complete: September.  All work is weather permitting.

27. State Route 2: Bridge Rehabilitation Project
Ottawa County (029-16):
  Through May, SR 2, between Rankie Road and West Carlton Road over Rusha Creek, is reduced to one lane for bridge deck replacement.  Traffic will be maintained by a traffic signal.  Project complete: June.  All work is weather permitting.

28. State Route 163: Bridge Rehabilitation Project

Ottawa County (304-15):  Through October, intermittent, short-term single lane restrictions are possible on the SR 163 lift bridge in Port Clinton for equipment/material drop off.  Future restrictions and closures will be announced.  Project complete: June 2017.  All work is weather permitting.

29. State Route 358: Railroad Repair *CLOSURE BEGINS MONDAY*

Ottawa County:  Effective Monday, May 16, though Monday, May 23, SR 358, between SR 2 and SR 163, will be closed for railroad repair.  Detour: SR 2; West Lakeshore Drive; SR 163.  All work is weather permitting.

30. State Route 19: Pavement Repair and Chip Seal

Sandusky County (1078-15):  Effective Monday, June 6, through August, SR 19, between US 20 and Academy Street, may be reduced to one lane for chip sealing.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

31. State Route 19: Pavement Repair and Chip Seal

Seneca County (1078-15):  Effective Monday, June 6, through August, SR 19, between SR 228 and SR 778, may be reduced to one lane for chip sealing.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

Williams/Fulton/Henry Counties

32.  U.S. 20A: Culvert Replacement

Williams County:  Through Friday, May 20, US 20A, between CR 21 and CR 22, is closed for culvert replacement.  Detour: SR 66; US 20; US 127.  All work is weather permitting.

 

33.  State Route 2: Culvert Replacement *UPDATE*

Williams County (506-15):  Effective Wednesday, June 1, through July, SR 2, between CR 19 and CR 20, will be closed for culvert replacement.  Detour: SR 191; US 6; SR 127.  Project complete: June.  All work is weather permitting.

 

34. State Route 15: Pavement Repair
Williams County (489-15):
  Through June, SR 15, between US 127 and CR O, may be reduced to one lane for pavement repair.  Traffic will be maintained by flaggers.  Additional restrictions and closures will be announced. Project complete: July.  All work is weather permitting.

35. State Route 34: Pavement Repairs

Williams County (1075-15):  Through May, intermittent lane restrictions are possible on SR 34, between SR 576 and CR D, for pavement repairs.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

36. State Route 49: Pavement Repairs

Williams County (1075-15):  Through May, intermittent lane restrictions are possible on SR 49, between US 20 and the Michigan border, for pavement repairs.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

37. State Route 107: Pavement Repair

Williams County:  Through July, SR 107, between Platt Street and Monroe Street in Montpelier, is closed for pavement repair.  Detour:  US 20A; US 20; SR 49.  Project complete: August.  For more information, contact the Village of Montpelier at 419-485-5543.  All work is weather permitting.

38. State Route 576: Culvert Replacement *UPDATE*
Williams County (506-15):  SR 576, between CR M and CR N30, is open.  Intermittent lane restrictions are possible for finish work.

39. State Route 108: Pavement Repairs

Fulton County (1075-15):  Through May, intermittent lane restrictions are possible on SR 108, between US 20 and the Michigan border, for pavement repairs.  Traffic will be maintained by flaggers. Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

 

40. State Route 120: Culvert Replacement *PROJECT COMPLETE*

Fulton County: SR 120, between SR 109 and CR 7, is open. The culvert replacement and drainage work is complete.

41. State Route 109: Damascus Bridge: Bridge Replacement *UPDATE*

Henry County (1-15):  Through Monday, May 16, lane restrictions are possible on CR 424 at SR 109 for culvert replacement.  Through October 2017, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work.  Work impacting traffic will be announced.  Project complete: October 2017.  All work is weather permitting.

42. State Route 109: Culvert Replacement *NEW PROJECT*

Henry County:  Effective Monday, May 23, through Friday, June 3, SR 109, between CR A and CR D, will be closed for culvert replacement.  Detour:  SR 18; SR 108; SR 613.  All work is weather permitting.

43. State Route 110: Slide Repair
Henry County (135-15
):  Through September, westbound SR 110, between CR P3 and Appian Avenue in Napoleon, is closed for slide repair.  Detour: CR P3, CR 12; Appian Avenue.  Eastbound SR 110 in this area will remain open and local access will be maintained.  Project complete: September.  All work is weather permitting. 

District Wide 

                                                                                                                                                      

44. Various Routes: Guardrail, Striping & Electrical Maintenance

District Wide (1053-15 & 1059-15 & 1044-15):  Through December, intermittent lane restrictions are possible district wide for guardrail, striping and electrical maintenance.  Project complete: December.  All work is weather permitting.