ODOT District 2 Weekly Construction Update – Aug. 25

ODOT District Two Weekly Construction Update – Thursday, August 25, 2016

 Updates are highlighted in bold and underlined.

Lucas/Wood Counties

1. Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions:  Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.  Through December, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through December, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.

Ramp Restrictions:

·         Through September, the ramp from northbound I-75 to westbound I-475 in Perrysburg is closed for bridge work.  Detour: SR 795 (Exit 195); southbound I-75.

·         Through September, the ramp from eastbound I-475 to northbound I-75 in Perrysburg is closed for bridge work.  Detour: southbound I-75; SR 582 (Exit 187).

·         Through September, the ramp from southbound I-75 to US 6 (Exit 179) is closed for pavement work.  Detour: Cygnet Road (Exit 171); SR 25.

·         Through September, the ramp from US 6 to southbound I-75 (Exit 66A) is closed for pavement work.  Detour: SR 25 (Exit 65); Cygnet Road.

·         Through October, southbound I-75 to westbound I-475 is reduced to one 11-foot lane for pavement installation.

Local Routes:
Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75.

Project complete: October 2017.  All work is weather permitting.

2. Interstate 75: Widening *LANE RESTRICTIONS BEGIN FRIDAY NIGHT*
Lucas County (485-14, 536-14):
  Effective Friday, August 26 at 9pm, through Monday, August 29 at 6am, northbound I-75, between Berdan Avenue and I-280, may be reduced to one lane for traffic pattern changes.  Additionally at this time, intermittent closures of the ramps to/from northbound I-75 to/from Stickney Avenue/South Expressway Drive (Exit 207), are possible.  Northbound I-75 to Stickney Avenue detour: Follow the northbound I-75 reroute to Manhattan Boulevard (Exit 12).  South Expressway Drive to northbound I-75 detour: Manhattan Boulevard to northbound I-75.

Effective Monday, August 29, through Thursday, September 1, nightly from 9pm until 6am, the ramp from northbound I-280 to southbound I-75 will be closed for bridge work.  Detour: northbound I-75; Alexis Road (Exit 210).

Through September 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for bridge work.  Through September, one lane of I-75 traffic is maintained in the current northbound lane and one lane of traffic is relocated to southbound I-75 and separated by barrier wall.

The following ramps are closed:

  • Through August, the ramp from Phillips Avenue to northbound I-75.  Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.
  • Through September, the ramp from southbound I-75 to Phillips Avenue (Exit 206).  Detour: North Expressway Drive (Exit 207); Stickney Avenue; South Expressway Drive.
  • Through September, the ramp from northbound I-75 to Jeep Parkway (Exit 205A).  Detour: Berdan Avenue (Exit 205B); Detroit Avenue.
  • Through September, the ramp from northbound I-75 to Phillips Avenue (Exit 206).  Detour: south Expressway Drive (Exit 207); Stickney Avenue; North Expressway Drive.
  • Through July 2018, the ramp from Jeep Parkway to southbound I-75.  Detour: Berdan Avenue.
  • Through July 2018, the ramp from Willys Parkway to northbound I-75.  Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue.
  • Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A).  Detour: Detroit Avenue (Exit 203B).

Local Streets:

Through October, South Expressway Drive is restricted to a single lane between Stickney Avenue and Lagrange Street.

Through October 2017, expect lane restrictions on Phillips Avenue at I-75 for bridge work.

Through September, Jeep Parkway from Central Avenue to Berdan Avenue is closed.  Detour: Central Avenue; Detroit Avenue; Berdan Avenue.

Through September, the ramp from northbound I-75 to Berdan Avenue is restricted to right turn only movements.  Suggested alternate route: Berdan Avenue; Detroit Avenue; Phillips Avenue; Haverhill Drive.

Through November, Elm Street and Wersell Avenue at South Expressway Drive, is closed.

Through May 2017, the Polish Village Overpass is closed for bridge work.  Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive.

Through July 2018, lane restrictions are possible on Detroit Avenue at I-75 for bridge work.

Through July 2018, expect lane restrictions on Berdan Avenue at I-75 for bridge work.

Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed.

Project complete: September 2018.  All work is weather permitting.

3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14): 
Through September, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes.  Overnight, 10pm through 6am, single lane restrictions are possible in this work zone.  Through October, Oakwood Avenue, between Wells Street and Grove Place, is closed for bridge work.  Seek alternate route.

Ramps restrictions and closures:

·         Through September, the interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.

·         Through September, the interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.

·         Through September, the ramp from D­etroit Avenue to southbound I-75 is closed.  Detour: Monroe Street; Michigan Avenue; SR 25.

·         Through September, the ramp from Detroit Avenue to northbound I-75 is closed.  Detour: Monroe Street; 14th Street.

·         Through September, the ramp from northbound I-75 to Bancroft Street (Exit 203A) is closed.  Detour: Detroit Avenue (Exit 203B); Monroe Street.

Project complete: September.  All work is weather permitting.

 

4. Interstate 75/280: Rerouting

Lucas County (536-14):  Through December, northbound I-75 traffic is rerouted to southbound I-280 for bridge replacement.  Two lanes of traffic will be maintained.  Reroute: southbound I-280; Central Avenue; northbound I-280.  Through December, Central Avenue, between Buckeye Street and Galena Street, is closed.  Detour: Lagrange Street; Greenbelt Parkway; Galena Street.  Pedestrian access will be maintained.

5. Interstate 75: Rest Area Closure

Wood County (170-14)Through December, the northbound and southbound I-75 rest areas are closed for renovations.  Project complete: December.  All work is weather permitting.

6. Interstate 280: Bridge Repair *NEW PROJECT*

Lucas County (1075-16):  Effective Tuesday, September 6, through October, southbound I-280, between Greenbelt Parkway (Exit 11) and Starr Avenue (Exit 8), may be reduced to two lanes for bridge repair.  Project complete: November.  All work is weather permitting.

7. Interstate 475: ProMedica Parkway Ramp
Lucas County:
  Through December, the ramp from ProMedica Parkway to eastbound I-475 is closed for traffic control.  Detour: westbound I-475; Douglas Road.  All work is weather permitting.

 

8. Interstate 475: Resurfacing and Bridge Project *WEEKEND LANE RESTRICTIONS*

Lucas County (58-16):  Effective Friday, August 26 at 8pm, through Monday, August 29 at 6am, westbound I-475 over Secor Road (Exit 17), will be reduced to one lane for bridge work.  Through September, 11-foot lane width restrictions are in place on I-475 over Secor Road (Exit 17) for bridge work.  Through September, overnight from 8pm until 6am, single lane restrictions are possible on I-475, between the US 23 interchange and Douglas Road, for resurfacing.  Additional restrictions may be announced.  Project complete: October.  All work is weather permitting.

9. Interstate 475: Bridge Widening

Lucas County (235-14):  Through September, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salisbury Road/Dussel Drive for pavement work.  Project complete: September.  All work is weather permitting.

10. Interstate Maintenance Work *UPDATE*

Lucas and Wood Counties:  Effective Sunday, August 28, through Tuesday, August 30, nightly from 9pm until 5am, the ramps to southbound I-75 from SR 25/Anthony Wayne Trail and from Erie Street may be closed for paving.  Detour: Anthony Wayne Trail; South Avenue.  Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work.  Project complete: December.  All work is weather permitting.

11. U.S. Route 20: Central Avenue Interchange Project
Lucas County (210-15):
 Through November, Central Avenue, between McCord Road and Van Fleet Parkway, is reduced to one lane. 11-foot lane width restrictions are in place within the work zone.

Through Monday, August 29 at 6am, the following ramps will be closed for pavement work:

·         Southbound I-475/US 23 to Central Avenue (Exit 13). Detour: Airport Highway (Exit 8A); northbound I-475.

·         Central Avenue to southbound I-475/US 23.  Detour: Northbound I-475; eastbound I-475; Secor Road (Exit 17); westbound I-475.

Through December, southbound US 23 traffic is reduced to one lane from the I-475/US 23 split in Sylvania to Central Avenue.  Through September 2017, overnight from 9pm until 6am, lane restrictions are possible on I-475/US 23 between Dorr Street and N. Holland Sylvania Road.  11-foot lane width restrictions are in place within the work zone.  Project complete: September 2017.  All work is weather permitting.

12. U.S. Route 20: Resurfacing and Turn Lanes
Lucas County (366-16): 
Through September, Central Avenue/US 20 at Herr Road, is reduced to one lane for turn lane construction.  Traffic will be maintained by a temporary traffic signal.
Through September, Herr Road north of US 20, is closed.  Detour: Sylvania Avenue; Centennial Road. The closure of Centennial Road north of US 20 has been postponed until further notice.  Additional restrictions and local road closures will be announced.  Project complete: November.  All work is weather permitting.

13. State Route 2: Resurfacing

Lucas County (246-16):  Through September, lane restrictions are possible on Airport Highway/SR 2, between Garden Road and the Lucas/Fulton County line.  Project complete: October.  All work is weather permitting.

 

14. State Route 2: Resurfacing and Bridge Project *UPDATE*
Lucas County (564-15):
  Through September, lane restrictions are possible on Airport Highway/SR 2, between Holloway Road and US 20A, for resurfacing.  Additional restrictions and closures may be announced.  Project complete: September.  All work is weather permitting.

15. State Route 2: Intersection Upgrades
Lucas County (142-15): 
Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on Airport Highway/SR 2 at Holland Sylvania Road, for intersection upgrades.  Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on SR 2/Airport Highway at Reynolds Road, for intersection upgrades.  Additional restrictions will be announced.  Project Complete: December.  All work is weather permitting.

16. State Route 2: Culvert Replacement

Lucas County (44-15):  Through Friday, September 16, Navarre Avenue/SR 2, between Cresceus Road and Patchen Road, is closed for culvert replacement.  Detour: I-280; Woodville Road/SR 51 (Exit 6B); Navarre Avenue.  Project complete: October.  All work is weather permitting.

 

17. State Route 2: Anthony Wayne Bridge Painting Project
Lucas County (220-16): 
Lane restrictions on the Anthony Wayne Bridge and additional local road closures will be announced.  Project complete: November 2017.  All work is weather permitting.

18. State Route 2: Resurfacing
Lucas County (8028-16): 
Through September, lane restrictions are possible on SR 2, between North Curtice Road and the Lucas/Ottawa county line.  Traffic will be maintained by flaggers.  Additional restrictions will be announced in Spring 2017.  Project complete: June 2017.  All work is weather permitting.

19. State Route 25: Safety Project
Lucas County (299-15):
  Through September, single, intermittent, lane restrictions are possible in both directions of the Anthony Wayne Trail, between Hippo Way and City Park Boulevard, for finish work.  Project complete: September.  All work is weather permitting.

 

20. State Route 51: Bridge Repair *UPDATE*

Lucas County (60-16):  Through August, Monroe Street/SR 51, between Parkview Avenue and Inwood Drive in Toledo, is reduced to one lane in each direction for bridge repair.  Through August, access to/from Monroe Street to/from North Cove Boulevard and Rosedale Avenue south of Monroe Street are maintained through right turn movements only.  Additionally at this time, South Cove Boulevard, Rosedale Avenue and Parkview Avenue, all north of Monroe Street, is closed.  Suggested alternate route: Upton Avenue or Auburn Avenue. Through September, intermittent lane restrictions are possible on Monroe Street/SR 51, between Parkview Avenue and Inwood Drive in Toledo, for finish work.  Project complete: September.  All work is weather permitting.

21. State Route 295: Railroad Repair *WORK COMPLETE*

Lucas County:  SR 295, between Patton Road and Pollock Road, is open.  The railroad repair work is complete.

22. Bancroft Street: Bridge Repair

Lucas County (59-16):  Through October, Bancroft Street, between Hollywood Avenue and Glenwood Avenue, is closed for bridge repair.  Detour: Collingwood Boulevard; Monroe Street.  Project complete: November.  All work is weather permitting.

23. Delaware Avenue: Bridge Rehabilitation

Lucas County (25-16):  Through September, Delaware Avenue, between Ayers Avenue and Kress Street in Toledo, is closed for bridge rehabilitation.  Detour: Delaware Avenue; Auburn Avenue; Central Avenue; Albion Street.  Project complete: October.  All work is weather permitting.

24. McCord Road: Underpass Construction *UPDATE*
Lucas County (236-14):  Through September, McCord Road between North Mall Drive/Hall Road and Spectrum Drive is closed to vehicular and pedestrian traffic. Detour: Holland Park Boulevard; North Mall Drive.  Holland Park Boulevard, between Angola Road and North Mall Drive, is now open.  The railroad relocation work is complete.  Project complete: November.  All work is weather permitting.

25. Rushland Avenue: Bridge Redecking
Lucas County (289-16):
  Through November, nightly from 7pm through 6am, lane restrictions are possible on I-475, at Rushland Avenue for bridge work.  Through November, Rushland Avenue between Groveland Road and Langenderfer Drive is closed for bridge deck replacement.  Detour: Langenderfer Drive; Bowen Road; Groveland Road.  Project complete: June 2018.  All work is weather permitting. 

26. Woodley Road: Bridge Repair Project

Lucas County (24-16):  Through October, shoulder restrictions are possible on I-475 at Woodley Road for bridge work.  Through August, Woodley Road, between Ellenridge Lane and Professional Drive, is closed for bridge repair.  Detour: Central Avenue; Talmadge Road; Sylvania Avenue.  Through August, overnight, from 8pm until 6am, single lane restrictions are possible on I-475, between Talmadge Road and Secor Road, for bridge repair.  Project complete: October.  All work is weather permitting.

27. U.S. Route 6: Pavement Reconstruction and Bridge Work *UPDATE*
Wood County (170-14):
  Through September, the ramp from southbound I-75 to eastbound US 6 is closed.  Detour: westbound US 6; SR 25. Through September, US 6, between SR 25 and Dunbridge Road, is reduced to one lane in each direction.  Lane widths are restricted to 11ft in this work zone.  Work complete: September.  All work is weather permitting.

 

28. U.S. Route 6: Resurfacing and Culvert Replacements
Wood County (373-16): 
Through August, US 6, between the Wood/Henry County line and SR 235, is closed for resurfacing and two culvert replacements.  Detour: SR 65; SR 281; SR 235.  Local access will be maintained.  Project complete: October.  All work is weather permitting.

29. U.S. Route 20: Resurfacing

Wood County (256-16):  Through November, lane restrictions are possible on US 20, between Lime City Road and SR 420, for resurfacing.  Traffic will be maintained by flaggers.  Project complete: June 2017.  All work is weather permitting.

 

30. State Route 51: Culvert Replacements
Wood County (618-15):
  Through August, SR 51, between Fostoria Road and Millbury Road, is closed for culvert replacement.  Detour: SR 795; I-280.  Project complete: September.  All work is weather permitting.

31. State Route 65: Soil Boring *CLOSURE BEGINS MONDAY*

Wood County:  Effective Monday, August 29, through Friday, September 2, SR 65, west of Forst Road will be closed for soil boring.  Detour: SR 64; SR 582.  All work is weather permitting.

32. State Route 105: Resurfacing and Sidewalk Repair

Wood County (90-16):  Through September, lane restrictions are possible on Front Street/SR 105, between Lemoyne Road and Pemberville Road, for finish work.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

33. State Route 105: Resurfacing

Wood County (257-16):  Through September, lane restrictions are possible on SR 105, between Dunbridge Road and SR 199, for resurfacing.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

34. State Route 199: Roundabout Construction *UPDATE*
Wood County (4004-16):
 Through September, Roachton Road west of SR 199 is closed for roundabout construction.  Detour: SR 199; SR 582; SR 25.  Effective Tuesday, September 6, through Thursday, September 15, SR 199 at Roachton Road will be closed for roundabout construction. Detour: SR 582; I-75; SR 795; US 20.  The closure of Roachton Road east of SR 199 will be announced.  Project complete: October.  All work is weather permitting.

35. State Route 199: Resurfacing and Sidewalk Repair

Wood County (90-16):  Through September, lane restrictions are possible on SR 199, between WestMillgrove Road and Elm Street in West Millgrove, for finish work.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

36. State Route 582: Drainage Work

Wood County:  Through Friday, August 26, daily from 7am until 4pm, SR 582, west of Pemberville Road, is closed for drainage work.  Detour: SR 199; SR 105; US 23.  All work is weather permitting.

37. State Route 795: Bridge Rehabilitation Project *UPDATE*
Wood County (300-16): 
Through September, westbound SR 795, between Cummings Road and Luckey Road, is reduced to one lane for bridge rehabilitation.  Additional restrictions may be announced.  Project complete: July 2017.  All work is weather permitting.

38. Cherry Street: Bridge Replacement

Wood County (3053-15):  Through October, Cherry Street, between Lennex Lane and Main Street in Millbury, will be closed for bridge replacement.  Detour: Bradner Road; SR 795; Main Street.  Project complete: November. All work is weather permitting.

39. Liberty Hi Road: Bridge Replacement

Wood County (3004-16):  Through October, Liberty Hi Road, between SR 281 and Bays Road, is closed for bridge replacement.  Detour: SR 281; SR 25; Cygnet Road.  Additionally through October Liberty Hi Road, between Mermill Road and Greensburg Pike, is closed for bridge replacement.  Detour: SR 281; SR 25; US 6; Sand Ridge Road.  Project complete: November. All work is weather permitting.

 

40. Lime City Road: Bridge Replacement
Wood County (3053-15): 
Through September, Lime City Road, between Marilyn Drive and Grassy Lane, is closed for bridge replacement.  Detour: Buck Road; Glenwood Road; Dixie Highway/SR 65.  Project Complete: November.  All work is weather permitting.

 

Ottawa/Sandusky/Seneca Counties

 

41. State Route 2: Lightner Road Bridge Widening *UPDATE*

Ottawa County (232-15):  Through September, intermittent lane restrictions are possible on SR 2, between SR 53/SE Catawba Road and SR 269, for bridge work.  Additionally, Lightner Road, between Kirk Road and East State Road, may be reduced to one lane for temporary pavement construction. Traffic will be maintained by flaggers.  Additional restrictions may be announced.
Project complete: September.  All work is weather permitting.

42. State Route 2: Bridge Rehabilitation Project *PROJECT COMPLETE*

Ottawa County (29-16):  Restrictions on SR 2, between Rankie Road and West Carlton Road over Rusha Creek, are lifted. The project is complete.

43. State Route 51: Resurfacing and Sidewalk Repair

Ottawa County (90-16):  Through September, lane restrictions are possible on SR 51, between I-80/I-90 Ohio Turnpike and SR 105, for bridge work.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

44. State Route 51: Pavement Repair

Ottawa and Wood Counties (194-16):  Through September, lane restrictions are possible on SR 51, between SR 163 and SR 579, for pavement repair.  Traffic will be maintained by flaggers.  Project complete: September.  All work is weather permitting.

45. State Route 163: Bridge Rehabilitation Project

Ottawa County (304-15):  Through October, intermittent, short-term single lane restrictions are possible on the SR 163 lift bridge in Port Clinton for equipment/material drop off.  Future restrictions and closures will be announced.  Project complete: June 2017.  All work is weather permitting.

46. U.S. Route 6: Resurfacing *PROJECT COMPLETE*

Sandusky County (156-16):  Lane restrictions on US 6, between CR 74 and SR 53, are lifted.  The resurfacing project is complete.

47. U.S. Route 20: Culvert Replacement
Sandusky County (155-16):
  Through August, US 20, between Spayd Road and Whirlpool Way, may be reduced to one lane for culvert repair.  Additionally, 11-foot lane width restrictions are in place in this zone.  Project complete: September.  All work is weather permitting.

48. State Route 53: Traffic Signal Upgrades

Sandusky County (301-16):  Through October, shoulder restrictions are possible on SR 53, between US 20 and Sean Street, for traffic signal upgrades. Additional restrictions may be announced.  Project Complete: November.  All work is weather permitting.

49. State Route 18: Bridge Replacement
Seneca County (406-16): 
Effective Tuesday, September 6, through November, SR 18, between CR 32 and TR 178 over Royer Ditch, will be closed for bridge replacement.  Detour: SR 162; SR 4; SR 269; US 20.  Project complete: December.  All work is weather permitting.

50. U.S. Route 23: Culvert Replacement *CLOSURE BEGINS MONDAY*

Seneca County:  Effective Monday, August 29, through Friday, September 9, US 23, between TR 108 and CR 18, will be closed for culvert replacement.  Detour: SR 18; SR 587; US 224.  All work is weather permitting.

51. State Route 12: Culvert Replacement

Seneca County:  Through Friday, August 26, SR 12, between TR 65 and TR 101, is closed for culvert replacements.  Detour: SR 635; SR 18.  All work is weather permitting.

52. State Route 53: Pavement Repair

Seneca County:  Through October, SR 53, between Miami Street and Hall Street in Tiffin, is closed for pavement repair.  Detour: US 224; SR 18; SR 635; SR 12.  Project complete: November.  For more information, contact the City of Tiffin at 419-448-5401.  All work is weather permitting.

53. State Route 101: Culvert Replacement *UPDATE*

Seneca County:  Effective Tuesday, September 6, through Monday, September 12, SR 101, between CR 38 and TR 76, will be closed for culvert replacement.  Detour: SR 18; SR 19.  All work is weather permitting.

54. State Route 162: Resurfacing

Seneca County (257-16):  Through September, lane restrictions are possible on SR 162, between SR 19 and TR 197, for resurfacing.  Traffic will be maintained by flaggers.  Project complete: October. All work is weather permitting.

55. State Route 587: Culvert Replacement *NEW WORK*

Seneca County:  Effective Wednesday, August 31, through Friday, September 9, SR 587, between TR 66 and TR 100, will be closed for culvert replacement.  Detour: SR 53; US 224.  All work is weather permitting.

Williams/Fulton/Henry Counties

56. State Route 2: Culvert Replacement  *UPDATE*

Williams County (506-15):  Through September, lane restrictions are possible on SR 2, between CR 19 and CR 20, for finish work.  Project complete: September.  All work is weather permitting.

 

57. State Route 15: Pavement Repair *UPDATE*
Williams County (489-15):
  Through September, lane restrictions are possible on SR 15, between US 127 and CR O, for finish work. Project complete: September.  All work is weather permitting.

58. State Route 576: Culvert Replacement *UPDATE*
Williams County (506-15):  Through September, intermittent lane restrictions are possible on SR 576, between CR M and CR N30, for finish work.  Project complete: September.  All work is weather permitting.

59. County Road 25: Bridge Replacement

Williams County (3009-16):  Through September, CR 25, between SR 34 and CR D, is closed for bridge replacement.  Detour: SR 34; CR 2425; CR D.  Project complete: October.  All work is weather permitting.

60. U.S. Route 20A: Resurfacing and Signal Upgrades

Fulton County (8016-16):  Through October, lane restrictions are possible on Airport Highway/US 20A, between the Lucas/Fulton County line and CR 3, for resurfacing and signal upgrades.  Project complete: January 2017.  All work is weather permitting.

61. State Route 109: Damascus Bridge: Bridge Replacement

Henry County (1-15):  Through September, lane restrictions are possible on CR 424 at SR 109 for paving.  Traffic will be maintained by flaggers.  Through May 2017, stop signs will be at the intersection of CR 424 at SR 109 for traffic control.  Through October 2017, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work.  Work impacting traffic will be announced.  Project complete: October 2017.  All work is weather permitting.

 

62. State Route 110: Slide Repair *PROJECT COMPLETE*
Henry County (135-15
):  Intermittent lane restrictions on SR 110, between CR P3 and Appian Avenue in Napoleon, are lifted.  The project is complete. 

63. Keyser Street: Bridge Replacement

Henry County (3004-16):  Through November, Keyser Street, between Marion Street and South Street in Deshler, is reduced to one lane for bridge replacement.  One lane of traffic will be maintained.  All work is weather permitting.

64. County Road 1: Bridge Replacement
Henry County (3004-16):  Through September, Henry County Road 1, between CR D/Oil Center Road and CR E/Hammansburg Road, is closed for bridge replacement.  Detour: SR 18; Custar Road; Cygnet Road.  Project complete: October.  All work is weather permitting.

District Wide 

                                                                                                                                                      

65. Various Routes: Guardrail, Striping & Electrical Maintenance

District Wide (1053-15 & 1059-15 & 1044-15):  Through December, intermittent lane restrictions are possible district wide for guardrail, striping and electrical maintenance.  Project complete: December.  All work is weather permitting.

66. Various Routes: Mowing

District Wide (1028-16):  Through October, intermittent lane and shoulder restrictions are possible district wide for mowing.  Project complete: December.  All work is weather permitting.

67. Various Routes: Raised Pavement Markers

District Wide (1055-15):  Through August, intermittent lane restrictions are possible district wide for raised pavement marker work.  Traffic will be maintained by flaggers. Project complete: October.  All work is weather permitting.

The Ohio Department of Transportation maintains the state’s largest man-made asset–the transportation system. ODOT’s mission is to provide the safe and easy movement of people and goods from place to place. As a $2.8 billion per year enterprise, ODOT invests the bulk of its resources in system preservation through maintenance, construction and snow and ice operations.

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.

Leave a Reply

Your email address will not be published. Required fields are marked *

NBX powered by PANDA Technologies
NBLS Website