ODOT District Two Weekly Construction Update – July 25

ODOT District Two Weekly Construction Update – July 25

Updates are highlighted in bold and underlined.

Lucas/Wood Counties

1. Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions:  Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.  Through December, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through December, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.

Ramp Restrictions:

·         Through September, the ramp from northbound I-75 to westbound I-475 in Perrysburg is closed for bridge work.  Detour: SR 795 (Exit 195); southbound I-75.

·         Through September, the ramp from eastbound I-475 to northbound I-75 in Perrysburg is closed for bridge work.  Detour: southbound I-75; SR 582 (Exit 187).

·         Through October, southbound I-75 to westbound I-475 is reduced to one 11-foot lane for pavement installation.

Local Routes:
Through July, Bays Road at I-75 is closed for bridge work.  Detour: SR 25; SR 281; Solether Road.

Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75.

Project complete: October 2017.  All work is weather permitting.

2. Interstate 75: Widening
Lucas County (485-14, 536-14):
  Effective Friday, July 22 at 9pm, through Saturday, July 23 at 10am, northbound I-75, between I-475 and Phillips Avenue, will be reduced to one lane for bridge work.  Through September 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for bridge work.  Through September, one lane of I-75 traffic is maintained in the current northbound lane and one lane of traffic is relocated to southbound I-75 and separated by barrier wall.

The following ramps are closed:

  • Through August, the ramp from Phillips Avenue to northbound I-75.  Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.
  • Through August, the ramp from southbound I-75 to Phillips Avenue (Exit 206).  Detour: North Expressway Drive (Exit 207); Stickney Avenue; South Expressway Drive.
  • Through September, the ramp from northbound I-75 to Jeep Parkway (Exit 205A).  Detour: Berdan Avenue (Exit 205B); Detroit Avenue.
  • Through September, the ramp from northbound I-75 to Phillips Avenue (Exit 206).  Detour: south Expressway Drive (Exit 207); Stickney Avenue; North Expressway Drive.
  • Through July 2018, the ramp from Jeep Parkway to southbound I-75.  Detour: Berdan Avenue.
  • Through July 2018, the ramp from Willys Parkway to northbound I-75.  Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue.
  • Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A).  Detour: Detroit Avenue (Exit 203B).

Local Streets:

Through August, South Expressway Drive is restricted to a single lane between Stickney Avenue and Lagrange Street.

Through August, expect lane restrictions on Phillips Avenue at I-75 for bridge work.

Through September, Jeep Parkway from Central Avenue to Berdan Avenue is closed.  Detour: Central Avenue; Detroit Avenue; Berdan Avenue.

Through September, the ramp from northbound I-75 to Berdan Avenue is restricted to right turn only movements.  Suggested alternate route: Berdan Avenue; Detroit Avenue; Phillips Avenue; Haverhill Drive.

Through November, Elm Street and Wersell Avenue at South Expressway Drive, is closed.

Through May 2017, the Polish Village Overpass is closed for bridge work.  Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive.

Through July 2018, lane restrictions are possible on Detroit Avenue at I-75 for bridge work.

Through July 2018, expect lane restrictions on Berdan Avenue at I-75 for bridge work.

Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed.

Project complete: September 2018.  All work is weather permitting.

3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14): 
Through August, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes.  Overnight, 10pm through 6am, single lane restrictions are possible in this work zone.  Through August, Oakwood Avenue, between Wells Street and Grove Place, is closed for bridge work.  Seek alternate route.

Ramps restrictions and closures:

·         Through August, the interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.

·         Through August, the interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.

·         Through August, the ramp from D­etroit Avenue to southbound I-75 is closed.  Detour: Monroe Street; Michigan Avenue; SR 25.

·         Through August, the ramp from Detroit Avenue to northbound I-75 is closed.  Detour: Monroe Street; 14th Street.

·         Through September, the ramp from northbound I-75 to Bancroft Street (Exit 203A) is closed.  Detour: Detroit Avenue (Exit 203B); Monroe Street.

Project complete: August.  All work is weather permitting.

 

4. Interstate 75/280: Rerouting

Lucas County (536-14):  Through December, northbound I-75 traffic is rerouted to southbound I-280 for bridge replacement.  Two lanes of traffic will be maintained.  Reroute: southbound I-280; Central Avenue; northbound I-280.  Through December, Central Avenue, between Buckeye Street and Galena Street, is closed.  Detour: Lagrange Street; Greenbelt Parkway; Galena Street.  Pedestrian access will be maintained.

5. Interstate 75: Rest Area Closure

Wood County (170-14)Through December, the northbound and southbound I-75 rest areas are closed for renovations.  Project complete: December.  All work is weather permitting.

6. Interstate 280: Bridge Deck Repairs

Lucas County (1056-15): Through July, shoulder restrictions are possible on the I-280 Veterans’ Glass City Skyway for bridge deck repairs.  Project complete: August.  All work is weather permitting.

7. Interstate 475: ProMedica Parkway Ramp
Lucas County:
  Through December, the ramp from ProMedica Parkway to eastbound I-475 is closed for traffic control.  Detour: westbound I-475; Douglas Road.  All work is weather permitting.

 

8. Interstate 475: Resurfacing and Bridge Project *UPDATE*

Lucas County (58-16):  Effective Friday, July 29, at 7pm until Monday, August 1 at 6am, I-475 at Secor Road will be reduced to one lane in each direction for bridge work.

 

Effective Monday, August 1, through Sunday, August 7, the ramp from northbound I-475/US 23 to eastbound I-475 will be reduced to one lane for barrier wall work.  

 

Effective Monday, August 1, through Sunday, August 7, nightly from 9pm until 5am, the following ramps may be closed for resurfacing:

·         From eastbound I-475 to Corey Road (Exit 15).  Detour: Secor Road (Exit 17); Central Avenue.

·         From Corey Road to westbound I-475. Detour: Central Avenue; Secor Road.

·         From westbound I-475 to Monroe Street (Exit 18A).  Detour: Secor Road (Exit 17).

·         From Monroe Street to eastbound I-475.  Detour: Douglas Road.

Through September, 11-foot lane width restrictions are in place on I-475 over Secor Road (Exit 17) for bridge work.  Through September, overnight from 8pm until 6am, single lane restrictions are possible on I-475, between the US 23 interchange and Douglas Road, for resurfacing.  Additional restrictions may be announced.  Project complete: October.  All work is weather permitting.

9. Interstate 475: Bridge Widening

Lucas County (235-14):  Through July, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salisbury Road/Dussel Drive for pavement work.  Project complete: August.  All work is weather permitting.

10. Interstate Maintenance Work

Lucas and Wood Counties:  Effective Friday, July 22, 8am until 4pm, single lane restrictions are possible on northbound I-280, between Ohio Turnpike (Exit 1) and SR 795 (Exit 2), for drain cleaning. Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work.  Project complete: December.  All work is weather permitting.

11. U.S. Route 20: Central Avenue Interchange Project
Lucas County (210-15):
 Through November, Central Avenue, between McCord Road and Van Fleet Parkway, is reduced to one lane. 11-foot lane width restrictions are in place within the work zone.

Through December, southbound US 23 traffic is reduced to one lane from the I-475/US 23 split in Sylvania to Central Avenue.  Through September 2017, overnight from 9pm until 6am, lane restrictions are possible on I-475/US 23 between Dorr Street and N. Holland Sylvania Road.  11-foot lane width restrictions are in place within the work zone.  Project complete: September 2017.  All work is weather permitting.

12. State Route 2: Resurfacing

Lucas County (246-16):  Through September, lane restrictions are possible on Airport Highway/SR 2, between Garden Road and the Lucas/Fulton County line.  Project complete: October.  All work is weather permitting.

 

13. State Route 2: Resurfacing and Bridge Project
Lucas County (564-15):
  Through August, lane restrictions are possible on Airport Highway/SR 2, between Holloway Road and US 20A, for resurfacing.  Additional restrictions and closures may be announced.  Project complete: September.  All work is weather permitting.

14. State Route 2: Intersection Upgrades
Lucas County (142-15): 
Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on Airport Highway/SR 2 at Holland Sylvania Road, for intersection upgrades.  Through November, nightly from 7pm until 6am, overnight lane restrictions are possible on SR 2/Airport Highway at Reynolds Road, for intersection upgrades.  Additional restrictions will be announced.  Project Complete: December.  All work is weather permitting.

15. State Route 2: Culvert Replacement *CLOSURE BEGINS MONDAY*

Lucas County (44-15):  Effective Monday, July 25, through August, Navarre Avenue/SR 2, between Cresceus Road and Patchen Road, will be closed for culvert replacement.  Detour: I-280; Woodville Road/SR 51 (Exit 6B); Navarre Avenue.  Project complete: September.  All work is weather permitting.

16. State Route 2: Anthony Wayne Bridge Painting Project *LOCAL CLOSURE BEGINS MONDAY*
Lucas County (220-16): 
Effective Monday, July 25, through Monday, August 1, Morris Street under the Anthony Wayne Bridge will be closed for bridge painting.  Detour: Ottawa Street; Broadway Street.  Lane restrictions on the Anthony Wayne Bridge and additional local road closures will be announced.  Project complete: November 2017.  All work is weather permitting.

17. State Route 25: Safety Project
Lucas County (299-15):
  Through July, single lane restrictions are possible on southbound (outbound from downtown Toledo) Anthony Wayne Trail, between Hippo Way and City Park Boulevard, for pavement rehabilitation.  Project complete: November.  All work is weather permitting.

 

18. State Route 51: Bridge Repair

Lucas County (60-16):  Through August, Monroe Street/SR 51, between Parkview Avenue and Inwood Drive in Toledo, is reduced to one lane in each direction for bridge repair.  Through August, access to/from Monroe Street to/from North Cove Boulevard and Rosedale Avenue south of Monroe Street will be maintained through right turn movements only.  Additionally at this time, South Cove Boulevard, Rosedale Avenue and Parkview Avenue, all north of Monroe Street, will be closed.  Suggested alternate route: Upton Avenue or Auburn Avenue. Additional restrictions or closures will be announced.  Project complete: September.  All work is weather permitting.

 

19. State Route 65: Bridge Deck Repairs *UPDATE*

Lucas County (1056-15):  Effective today until 4pm, and on Monday, July 25, and Tuesday, July 26, daily from 9am until 4pm, the Craig Memorial Bridge/SR 65 will be closed to vehicular and pedestrian traffic for bridge repair.  Detour: Front Street; Main Street/Cherry Street; Summit Street.  Marine access will be maintained.  The bridge will remain open through the weekend.  Through July, expect lane and shoulder restrictions on the Robert Craig Memorial Bridge/SR 65 in Toledo for bridge repair.  Additional restrictions may be announced.  Project complete: August.  All work is weather permitting.

20. Bancroft Street: Bridge Repair

Lucas County (59-16):  Through October, Bancroft Street, between Hollywood Avenue and Glenwood Avenue, is closed for bridge repair.  Detour: Collingwood Boulevard; Monroe Street.  Project complete: November.  All work is weather permitting.

21. Delaware Avenue: Bridge Rehabilitation

Lucas County (25-16):  Through September, Delaware Avenue, between Ayers Avenue and Kress Street in Toledo, is closed for bridge rehabilitation.  Detour: Delaware Avenue; Auburn Avenue; Central Avenue; Albion Street.  Project complete: October.  All work is weather permitting.

22. McCord Road: Underpass Construction
Lucas County (236-14):  Through September, McCord Road between North Mall Drive/Hall Road and Spectrum Drive is closed to vehicular and pedestrian traffic.  Detour: Holland Park Boulevard; North Mall Drive.  Effective Thursday, July 28 through Monday, August 22, Holland Park Boulevard, between Angola Road and North Mall Drive, will be closed for railroad relocation.  Detour: Angola Road; Holland Sylvania Road; Airport Highway; McCord Road.  Local access will be maintained.  Project complete: November.  All work is weather permitting.

23. Rushland Avenue: Bridge Redecking
Lucas County (289-16):
  Effective, Monday, July 25, through November, nightly from 7pm through 6am, lane restrictions are possible on I-475, at Rushland Avenue for bridge work.  Effective Monday, August 1, through November, Rushland Avenue between Groveland Road and Langenderfer Drive will be closed for bridge deck replacement.  Detour: Langenderfer Drive; Bowen Road; Groveland Road.  Project complete: June 2018.  All work is weather permitting. 

24. Woodley Road: Bridge Repair Project *UPDATE*

Lucas County (24-16):  Through October, shoulder restrictions are possible on I-475 at Woodley Road for bridge work.  Through August, Woodley Road, between Ellenridge Lane and Professional Drive, is closed for bridge repair.  Detour: Central Avenue; Talmadge Road; Sylvania Avenue.  Through July, overnight, from 8pm until 6am, single lane restrictions are possible on I-475, between Talmadge Road and Secor Road, for bridge repair.   Project complete: October.  All work is weather permitting.

25. U.S. Route 6: Pavement Reconstruction and Bridge Work
Wood County (170-14):
  Through August, the ramp from southbound I-75 to eastbound US 6 is closed.  Detour: westbound US 6; SR 25.  Through August, US 6, between SR 25 and Dunbridge Road, is reduced to one lane in each direction.  Lane widths are restricted to 11ft in this work zone.  Work complete: August.  All work is weather permitting.

 

26. U.S. Route 6: Resurfacing and Culvert Replacements
Wood County (373-16): 
Through August, US 6, between the Wood/Henry County line and SR 235, is closed for resurfacing and two culvert replacements.  Detour: SR 65; SR 281; SR 235.  Local access will be maintained.  Project complete: October.  All work is weather permitting.

27. U.S. Route 23: Culvert Replacements

Wood County:  Through Friday, July 29, US 23, between US 6 and Risingsun, is closed for culvert replacements.  Detour: US 6; SR 199.  Local access will be maintained.  All work is weather permitting.

 

28. State Route 51: Culvert Replacements
Wood County (618-15):
  Through July, SR 51, between Owen Road and Pemberville Road, is closed for culvert replacement.  Detour: SR 795; I-280.  Additional closures will be announced.  Project complete: September.  All work is weather permitting.

29. State Route 105: Resurfacing and Sidewalk Repair

Wood County (90-16):  Through July, lane restrictions are possible on Front Street/SR 105, between Lemoyne Road and Pemberville Road for resurfacing.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

30. State Route 163: Culvert Replacement *NEW WORK*

Wood County:  Effective Thursday, August 4 through Friday, August 5, SR 163 at Luckey Road will be closed for culvert replacement.  Detour: US 20; SR 420.  All work is weather permitting.

31. State Route 199: Roundabout Construction
Wood County (4004-16):
 Through September, Roachton Road west of SR 199 is closed for roundabout construction.  Detour: SR 199; SR 582; SR 25.  The closure of Roachton Road east of SR 199 will be announced.  Project complete: October.  All work is weather permitting.

32. State Route 199: Resurfacing and Sidewalk Repair

Wood County (90-16):  Through July, lane restrictions are possible on SR 199, between West Millgrove Road and Elm Street in West Millgrove, for resurfacing.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

33. State Route 199: Culvert Replacement *NEW WORK*

Wood County:  Effective Monday, August 1, through Friday, August 5, SR 199, between SR 105 and Sugar Ridge Road, will be closed for culvert replacement.  Detour: SR 105; US 23; SR 582.  All work is weather permitting.

34. State Route 281: Culvert Replacement *WORK DELAYED*

Wood County:  The closure of SR 281 at Mermill Road for culvert replacement has been delayed until further notice.

35. Libbey Road: Pavement Reconstruction

Wood County (256-16):  Through August, Libbey Road, between Lemoyne Road and SR 420, is closed for pavement reconstruction.  Detour: Lemoyne Road; SR 163; SR 420.  Project complete: June 2017.  All work is weather permitting.

36. Lime City Road: Bridge Replacement
Wood County (3053-15): 
Through September, Lime City Road, between Marilyn Drive and Grassy Lane, is closed for bridge replacement.  Detour: Buck Road; Glenwood Road; Dixie Highway/SR 65.  Project Complete: November.  All work is weather permitting.

 

Ottawa/Sandusky/Seneca Counties

 

37. State Route 2: Lightner Road Bridge Widening

Ottawa County (232-15):  Through August, intermittent lane restrictions are possible on SR 2, between SR 53/SE Catawba Road and SR 269, for bridge work.  Additionally, Lightner Road, between Kirk Road and East State Road, may be reduced to one lane for temporary pavement construction. Traffic will be maintained by flaggers.  Additional restrictions will be announced.
Project complete: September.  All work is weather permitting.

38. State Route 2: Bridge Rehabilitation Project

Ottawa County (29-16):  Through July, intermittent lane restrictions are possible on SR 2, between Rankie Road and West Carlton Road over Rusha Creek, for bridge deck work.  Traffic will be maintained by flaggers.  Project complete: July.  All work is weather permitting.

39. State Route 51: Resurfacing and Sidewalk Repair

Ottawa County (90-16):  Through July, lane restrictions are possible on SR 51, between I-80/I-90 Ohio Turnpike and SR 105, for bridge work and resurfacing.  Traffic will be maintained by flaggers.  Project complete: October.  All work is weather permitting.

40. State Route 51: Pavement Repair

Ottawa County (194-16):  Through July, lane restrictions are possible on SR 51, between SR 163 and SR 579, for pavement repair.  Traffic will be maintained by flaggers.  Project complete August.  All work is weather permitting.

41. State Route 163: Bridge Rehabilitation Project

Ottawa County (304-15):  Through October, intermittent, short-term single lane restrictions are possible on the SR 163 lift bridge in Port Clinton for equipment/material drop off.  Future restrictions and closures will be announced.  Project complete: June 2017.  All work is weather permitting.

42. U.S. Route 6: Resurfacing

Sandusky County (156-16):  Through August, US 6, between CR 74 and SR 53, may be reduced to one lane for resurfacing.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

43. U.S. Route 20: Culvert Replacement
Sandusky County (155-16):
  Through August, US 20, between Spayd Road and Whirlpool Way, may be reduced to one lane for culvert repair.  Additionally, 11-foot lane width restrictions are in place in this zone.  Project complete: September.  All work is weather permitting.

 

44. State Route 19: Pavement Repair and Chip Seal

Sandusky County (1078-15):  Through August, SR 19, between US 20 and Academy Street, may be reduced to one lane for finish work.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

45. State Route 53: Traffic Signal Upgrades *NEW PROJECT*

Sandusky County (301-16):  Effective Monday, July 25, through August, shoulder restrictions are possible on SR 53, between US 20 and Sean Street, for traffic signal upgrades. Additional restrictions may be announced.  Project Complete: November.  All work is weather permitting.

46. State Route 19: Pavement Repair and Chip Seal

Seneca County (1078-15):  Through August, SR 19, between SR 228 and SR 778, may be reduced to one lane for finish work.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

47. State Route 53: Pavement Repair

Seneca County:  Through October, SR 53, between Miami Street and Hall Street in Tiffin, is closed for pavement repair.  Detour: US 224; SR 18; US 23; SR 12.  Project complete: November.  For more information, contact the City of Tiffin at 419-448-5401.  All work is weather permitting.

Williams/Fulton/Henry Counties

48. State Route 2: Culvert Replacement 

Williams County (506-15):  Through August, lane restrictions are possible on SR 2, between CR 19 and CR 20, for finish work.  Project complete: August.  All work is weather permitting.

 

49. State Route 15: Pavement Repair
Williams County (489-15):
  Through August, lane restrictions are possible on SR 15, between US 127 and CR O, for finish work. Project complete: August.  All work is weather permitting.

50. State Route 34: Pavement Repairs

Williams County (1075-15):  Through July, intermittent lane restrictions are possible on SR 34, between SR 576 and CR D, for pavement repairs.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

51. State Route 49: Pavement Repairs

Williams County (1075-15):  Through July, intermittent lane restrictions are possible on SR 49, between US 20 and the Michigan border, for pavement repairs.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

52. State Route 107: Pavement Repair

Williams County:  Through July, SR 107, between Platt Street and Monroe Street in Montpelier, is closed for pavement repair.  Detour:  US 20A; US 20; SR 49.  Project complete: August.  For more information, contact the Village of Montpelier at 419-485-5543.  All work is weather permitting.

53. State Route 576: Culvert Replacement
Williams County (506-15):  Through July, intermittent lane restrictions are possible on SR 576, between CR M and CR N30, for finish work.  Project complete: August. All work is weather permitting.

54. County Road 25: Bridge Replacement

Williams County (3009-16):  Through September, CR 25, between SR 34 and CR D, will be closed for bridge replacement.  Detour: SR 34; CR 2425; CR D.  Project complete: October.  All work is weather permitting.

55. State Route 108: Pavement Repairs 

Fulton County (1075-15):  Through July, intermittent lane restrictions are possible on SR 108, between US 20 and the Michigan border, for pavement repairs.  Traffic will be maintained by flaggers.  Additional restrictions will be announced.  Project complete: August.  All work is weather permitting.

56. State Route 109: Damascus Bridge: Bridge Replacement *CLOSURE NEXT WEEK*

Henry County (1-15):  Effective Thursday, July 28, through Monday, August 8, SR 109, between CR 424 and CR S will be closed for pavement repair.  Detour: CR 424; Industrial Drive; US 24.  Through October 2017, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work.  Work impacting traffic will be announced.  Project complete: October 2017.  All work is weather permitting.

 

57. State Route 110: Slide Repair
Henry County (135-15
):  Through September, westbound SR 110, between CR P3 and Appian Avenue in Napoleon, is closed for slide repair.  Detour: CR P3, CR 12; Appian Avenue.  Eastbound SR 110 in this area will remain open and local access will be maintained.  Project complete: September.  All work is weather permitting. 

58. State Route 281: Culvert Replacement *WORK COMPLETE*

Henry County:  SR 281, between TR 15 and CR 14, is open.  The culvert replacement work is complete.  All work is weather permitting.

59. Keyser Street: Bridge Replacement

Henry County (3004-16):  Through November, Keyser Street, between Marion Street and South Street in Deshler, is reduced to one lane for bridge replacement.  One lane of traffic will be maintained.  All work is weather permitting.

60. County Road 1: Bridge Replacement
Henry County (3004-16):  Through September, Henry County Road 1, between CR D/Oil Center Road and CR E/Hammansburg Road, is closed for bridge replacement.  Detour: SR 18; Custar Road; Cygnet Road.  Project complete: October.  All work is weather permitting.

District Wide 

                                                                                                                                                      

61. Various Routes: Guardrail, Striping & Electrical Maintenance

District Wide (1053-15 & 1059-15 & 1044-15):  Through December, intermittent lane restrictions are possible district wide for guardrail, striping and electrical maintenance.  Project complete: December.  All work is weather permitting.

62. Various Route: Mowing

District Wide (1028-16):  Through October, intermittent lane and shoulder restrictions are possible district wide for mowing.  Project complete: December.  All work is weather permitting.

The Ohio Department of Transportation maintains the state’s largest man-made asset–the transportation system. ODOT’s mission is to provide the safe and easy movement of people and goods from place to place. As a $2.8 billion per year enterprise, ODOT invests the bulk of its resources in system preservation through maintenance, construction and snow and ice operations.

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.