ODOT District Two Weekly Construction Update – July 9

I - 75 south to Eagleville Exit
I – 75 south to Eagleville Exit from the Oil Center Rd. Overpass – Click image to enlarge
I - 75 1 north at Oil Center
I – 75 to the north at Oil Center toward Cygnet

Lucas/Wood Counties

1. Interstate 75: Widening *UPDATE*
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):

Interstate Restrictions:
Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.

Through December, one lane of northbound I-75 traffic, from Roachton Road to US 20, is maintained in the northbound lane and one lane of northbound I-75 traffic, from Roachton Road to US 20, is maintained on southbound I-75.  Through 2016, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through 2016, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.

Ramp Restrictions:
Through December, the ramp from southbound I-75 to westbound I-475 is reduced to one lane.  The ramp from eastbound I-475 to northbound I-75 is permanently reduced to one lane. 

Local Routes:
Effective Monday, July 13, through November, Jerry City Road at I-75 will be closed for bridge work.  Detour: SR 25; SR 281; Solether Road.

Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75.  Project complete: October 2017.  All work is weather permitting.

2. Interstate 75: Widening *UPDATE*
Lucas County (485-14, 536-14):
Effective tonight at 10pm, through Friday, July 10 at 6am, lane restrictions are possible on eastbound I-475, between ProMedica Parkway and the I-75/I-475 interchange in Toledo, for pavement marking.  Additionally at this time, the ramp from eastbound I-475 to northbound I-75 will be closed for pavement marking.  Detour: southbound I-75; Washington Street (Exit 202A). 

Through July 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for bridge work.  Through fall 2016, one lane of I-75 traffic is maintained in the current northbound lane and one lane of traffic is relocated to southbound I-75 and separated by barrier wall.

The following ramps are closed:

·         Through November 2016, the ramp from northbound I-75 to Phillips Avenue (Exit 206).  Detour: south Expressway Drive (Exit 207); Stickney Avenue; North Expressway Drive.

·         Through June 2016, the ramp from southbound I-75 to Phillips Avenue (Exit 206).  Detour: North Expressway Drive (Exit 207); Stickney Avenue; South Expressway Drive.

·         Through June 2016, the ramp from Phillips Avenue to northbound I-75.  Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.

·         Through July 2016, the ramp from northbound I-75 to Jeep Parkway (Exit 205A).  Detour: Berdan Avenue (Exit 205B); Detroit Avenue.

·         Through July 2018, the ramp from Jeep Parkway to southbound I-75.  Detour: Berdan Avenue.

·         Through July 2018, the ramp from Willys Parkway to northbound I-75.  Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue.

·         Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A).  Detour: Detroit Avenue (Exit 203B).

Local Streets:

Through November 2016, the ramp from northbound I-75 to Berdan Avenue is restricted to right turn only movements.  Suggested alternate route: Berdan Avenue; Detroit Avenue; Phillips Avenue; Haverhill Drive.

Through May 2017, the Polish Village Overpass is closed for bridge work.  Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive.

Through July, expect lane restrictions on Phillips Avenue at I-75, on Lagrange Street at I-75, and on Stickney Avenue at I-75 for bridge work.

Through October, South Expressway Drive will be restricted to a single lane between Stickney Avenue and Lagrange Street.

Through June 2016, Jeep Parkway from Central Avenue to Berdan Avenue is closed.  Central Avenue; Detroit Avenue; Berdan Avenue.

Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed.

Project complete: July 2018.  All work is weather permitting.

3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14):
Through July, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes. Overnight, 10pm through 6am, single lane restrictions are possible in this work zone.

Ramp closures:

•      Through August, the ramp from northbound I-75 to Bancroft Street is closed.  Detour: Berdan Ave (Exit 205B); Detroit Avenue. 

•      Through August, the ramp from Collingwood Boulevard to northbound I-75 is closed.  Detour:  Dorr Street; Washington Street; 14th Street.

Through August 2016, the following ramps will be restricted or closed:

·         The interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.

·         The interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.

·         The ramp from Detroit Avenue to southbound I-75 is closed.  Detour: Monroe Street; Michigan Avenue; SR 25.

Through May 2016, Oakwood Avenue, between Wells Street and Grove Place, is closed for bridge work.  Seek alternate route.  Project complete: August 2016.  All work is weather permitting.

4. Interstate 75: Pavement Repair *NEW WORK*

Lucas County:  Effective Sunday, July 12, through Tuesday, July 14, nightly from 9pm to 5am, lane restrictions are possible on southbound I-75, between the Anthony Wayne Trail and South Avenue, for pavement repair.   Additionally at this time, the ramp from Erie Street to southbound I-75 will be closed.  Detour: Anthony Wayne Trail; South Avenue.  All work is weather permitting.

5. Interstate 280: Sensor Installation *LANE RESTRICTION ON FRIDAY*

Lucas County: Effective Friday, July 10, from 9am until 3pm, single lane restrictions are possible on northbound I-280 on the Veterans’ Glass City Skyway for sensor installation.  All work is weather permitting.

6. Interstate 475: ProMedica Parkway Ramp
Lucas County:
  Through 2016, the ramp from ProMedica Parkway to eastbound I-475 is closed for traffic control.  Detour: westbound I-475; Douglas Road.  All work is weather permitting.

7. Interstate 475/U.S. Route 23: Interchange Upgrade
Lucas County (184-14):
Overnight lane restrictions are possible at the interchange of I-475/US 23 from Central Avenue to N. Holland Sylvania Road.  Through July, lane restrictions are possible on Blossman Road, between Moffet Road and Plainview Drive for bridge work.  Traffic will be maintained by flaggers.  Project complete: December.  All work is weather permitting.

8. Interstate 475: Bridge Widening
Lucas County (251-13 & 235-14):
 Through October, the ramp from westbound Airport Highway to northbound I-475 will be closed.   Detour: southbound I-475; Salisbury Road/Dussel Drive (Exit 6).

Through May 2016, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salisbury Road/Dussel Drive.  11-foot lane width restrictions are in place on I-475, between Angola Road and Salisbury Road/Dussel Drive.  Through June 2016, lane and shoulder restrictions are possible on the Ohio Turnpike (I-80/I-90) at the I-475 bridge.  Through July, Manley Road at the Ohio Turnpike Bridge is closed.  Project complete: June 2016.  All work is weather permitting.  

9. Interstate 475: Noise Wall Installation

Lucas County (314-14): Through July, weekdays from 10am until 4pm, and on Saturdays from 7:30am until 4pm, intermittent lane and shoulder restrictions are possible on I-475, between Corey Road and Talmadge Road, for noise wall installation.  Through July, overnight, 9pm through 6am, lane restrictions are possible on I-475 from Corey Road to Woodley Road.  Project complete: July.  All work is weather permitting.

10. Interstate 475: Bridge Deck Replacement
Lucas County (480-14):
Through August, overnight from 9pm until 6am, single lane restrictions are possible on I-475 at Bancroft Street for bridge replacement.  Through August, expect shoulder restrictions on I-475 at Bancroft Street for bridge repair.  Through August, expect lane restrictions on Bancroft Street at I-475 for finish work.  Project complete: August.  All work is weather permitting.

11. Interstate 475: Pavement Work

Wood County: Through July, overnight from 7pm to 6am, single lane restrictions are possible on I-475 in both directions between SR 25 and US 24 for pavement work.  Weekend work will be announced.  All ramps will remain open.  All work is weather permitting.

12. Interstate Maintenance Work

Lucas and Wood Counties:  Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work.  Project complete: December.  All work is weather permitting.

13. U.S. Route 20: Holland Sylvania Road & Reynolds Road Intersection Improvements
Lucas County (145-14 & 252-14):
 Through July, lane restrictions are possible on Central Avenue from Fairbanks Avenue to Reynolds Road for median installation.  Additionally, through July, expect lane restrictions on Holland-Sylvania Road, between Huntingfield Boulevard to Bonsels Parkway for median installation.  Through July, intermittent lane restrictions are possible at the intersection of Central Avenue and Reynolds Road for safety improvements.  Project complete: July.  All work is weather permitting.
14. State Route 2: Anthony Wayne Bridge Project

Lucas County (58-13):  Through July, Miami Street between Nevada Street and Greenwood Avenue, is closed for bridge work.  Detour: Fassett Street; Oak Street. Through October, short-term intermittent, closures are possible on Yondota Street, Utah Street, Morris Street and Ottawa Street for bridge work.  Through November, the Anthony Wayne Bridge is closed to vehicular and pedestrian traffic.  Detour: Oak Street; Fassett Street; Miami Street; I-75; Anthony Wayne Trail (Exit 201B); Monroe Street; Summit Street.  Project complete: December.  All work is weather permitting.

15. State Route 25: Safety Project
Lucas County (299-15):
  Through November 2016, the Anthony Wayne Trail, between Hippo Way and City Park Boulevard, may be reduced to two lanes for intersection safety improvements and pavement replacement.  Effective Friday, July 31, through Monday, August 3, South Avenue at the Anthony Wayne Trail will be closed to through traffic, with only right turn movements permitted. Additional closures will be announced.  Project complete: November 2016.  All work is weather permitting.

16. State Route 64: Roundabout and Realignment

Lucas County (143-15) Through August, SR 64, at Finzel Road will be closed for roundabout construction.  Detour: SR 295; US 24.  Additionally, Finzel Road south of SR 64 will be closed.  Finzel Road north of SR 64 will remain open at this time.  Additional closures of Finzel Road will be announced.  Project complete: October.  All work is weather permitting. 

17. McCord Road: Underpass Construction
Lucas County (236-14):
Through August, North Mall Drive/Hall Street at McCord Road will be closed.  Local business access will be maintained.  Through September 2016, McCord Road between North Mall Drive/Hall Road and Spectrum Drive is closed to vehicular and pedestrian traffic.  Detour: Airport Highway; Holland Sylvania; Angola Road.   Project complete: November 2016.  All work is weather permitting.

18. Various Routes: Bridge Painting
Lucas County (8027-14):
  Through July, overnight 6pm through 6am, lane restrictions are possible on US 24 at Fallen Timbers Lane for bridge painting.  Additionally, at this time, lane restrictions are possible on Fallen Timbers Lane.  Project complete: December.  All work is weather permitting.

19. U.S. Route 6: Pavement Reconstruction and Bridge Work
Wood County (170-14):
  Through October, the ramp from southbound I-75 to eastbound US 6 is closed.  Detour: westbound US 6; SR 25; Cygnet Road; I-75.  Through October, US 6, between SR 25 and Dunbridge road, is reduced to one lane in each direction.  Lane widths are restricted to 11ft in this work zone.  Work complete: October.  All work is weather permitting.

20. U.S. Route 6:  Resurfacing and Bridge Work
Wood County (434-14): Through August, the ramp from SR 25 to eastbound US 6 is closed for bridge repair.  Detour: Cygnet Road; I-75.  Through July, intermittent lane restrictions are possible on US 6, between County Home Road and SR 199 for resurfacing.  Traffic will be maintained by flaggers.  Through August, US 6, between Rudolph Road and Klopfenstein Road is reduced to one lane in each direction for bridge repair.  Project complete: September.  All work is weather permitting.

21. U.S. Route 20: Culvert Replacement
Wood County (8002-15):
  Through July, US 20, between SR 163 and SR 420 will be closed for culvert replacement.  Detour: SR 420; SR 163.  Project complete: August.  All work is weather permitting.

22. State Route 64: Slide Repair
Wood County (155-15):
  Through September, intermittent lane restrictions are possible on SR 64, between Reitz Road and SR 64/65 Waterville Bridge for slide repair.  Traffic will be maintained by flaggers. Beginning Monday, July 13, through August, a temporary traffic signal will be installed to maintain one lane of traffic through the work area.  Project complete: November.  All work is weather permitting.

23. State Route 65: Resurfacing
Wood County (587-14):
  Through July, daytime intermittent lane restrictions are possible on SR 65, between SR 235 to SR 64 for resurfacing.  Lane width restrictions of 10.5 feet are possible in this work zone.  Traffic will be maintained by flaggers.  Project complete: August.  All work is weather permitting.

24. State Route 65:  Slope Repair

Wood County (119-15):  Through September, SR 65, between Weston Road through Benschoter Road, will be closed for slope repair.  Detour: SR 235; US 6; SR 65.  Project complete: September.  All work is weather permitting.

25. State Route 420: Safety Improvements *UPDATE*

Wood County (423-14): Through Monday, July 13, the ramp from Ohio Turnpike to northbound I-280 will be closed.  Detour: southbound I-280/SR 420; use J-turn south of Libbey Road; northbound I-280/SR 420.  Through July, intermittent lane restrictions and delays are possible on SR 420, between SR 163 and I-80/I-90, for pavement work.  The left turn lane from southbound SR 420 to Libbey Road ispermanently closed.  Motorists should use the newly built turnaround. 11-foot lane width restrictions are in place on northbound SR 420.  Project complete: August.  All work is weather permitting.

26. State Route 582: Bridge Rehabilitation

Wood County (154-15):   Through August, SR 582, between Stony Ridge Road and Layman Road will be closed for bridge rehabilitation.  Detour: SR 199; SR 105; US 23.  Project complete: September.  All work is weather permitting. 

27. Gypsy Lane Road: Bridge Repair 

Wood County (1093-14): Through July, Gypsy Lane Road over I-75 is reduced to one lane for bridge repair.  Traffic is maintained by automated signal.  Project complete: July.  All work is weather permitting.

28. Park Avenue: Bridge Replacement

Wood County (3028-15): Through August, Park Avenue in Fostoria, between Lincoln Avenue and Kennedy Lane will be closed for bridge replacement.  Detour: North County Line Road (US 23/SR 199); Summit Street; Vine Street.  Project complete: August.  All work is weather permitting.

Ottawa/Sandusky/Seneca Counties

29. State Route 53: Bridge Repair

Ottawa County: Through July, lane restrictions are possible on the ramp from SR 53/West Fremont Road to eastbound SR 2 for pavement work.  Ramp access is maintained.  All work is weather permitting.

30. U.S. Route 6: Roundabout Construction *NEW PROJECT*
Sandusky County (8018-15
):  Effective Monday, July 20, through August, shoulder restrictions are possible on US 6/SR 53, between Napoleon Road to W. State Street, for roundabout construction.  Lane restrictions on US 6/SR 53 and the closure of Muskellunge Creek Road will be announced.  Project complete: November.  All work is weather permitting.

31. State Route 12: Bridge Rehabilitation

Sandusky and Seneca Counties (433-14): Through July, intermittent lane restrictions are possible on SR 12, between SR 53 and Franklin Street in Bettsville for finish work. Project complete: July.  All work is weather permitted.

32. State Route 412: Culvert Replacement

Sandusky County (324-14):  Through July, SR 412, between N. County Road 198 and Karbler Road, is closed for culvert replacement.  Detours: US 20; SR 510.  Through July, intermittent lane restrictions are possible on SR 412, between TR 274 and SR 101 for chip sealing.  Traffic will be maintained by flaggers.  Project complete: July.  All work is weather permitted.

33. State Route 590: Bridge Replacement
Sandusky County (534-14):  Through July, SR 590, between Burgoon Road and Kenan-Hite Road, will be closed for bridge replacement.  Detour: US 6; SR 635; SR 12; SR 53.  Project complete: August.  All work is weather permitting.

34. State Route 18: Resurfacing *NEW PROJECT*

Seneca County (97-15):  Effective Monday, July 13, through August, intermittent lane restrictions are possible on SR 18, between TR 159 and SR 67/SR 18 for resurfacing.  Project complete: September.  All work is weather permitting.

35. State Route 53: Railroad Repair *NEW WORK*
Seneca County:
Effective Monday, July 20 through July, SR 53, between CR 40 and CR 51, will be closed for railroad repair. Detour: SR 18; SR 635; SR 12. All work is weather permitting.

36. State Route 100: Culvert Replacement *NEW PROJECT*
Seneca County (236-15):
  Effective Monday, July 13, through August, SR 100, between SR 67 and TR 44, will be closed for culvert replacement.  Detour: SR 67; SR 100.  Project complete: August.  All work is weather permitting.

37. U.S. Route 224: Resurfacing

Seneca County (50-15):  Through July, intermittent lane restrictions are possible on US 224, between Miller Drive and Township Road 197, for finish work.  Traffic will be maintained by flaggers.  Project complete: July.  All work is weather permitting.

38. State Route 587: Culvert Replacement *UPDATE*
Seneca County (281-15 &
55-15):  Through August, SR 587, between TR 90/Sauber Road and TR 56/Arendt Road, will be closed for culvert replacement.  Additionally, Monday, July 13, through August,SR 587 between CR 18 and TR 112, will be closed for culvert replacement.  Detour: SR 53; US 224; SR 18.  Project complete: October.  All work is weather permitting.

Williams/Fulton/Henry Counties

39. U.S. Route 6: Culvert Replacement
Williams County (534-14):
 Through July, US 6, between CR 5.5 and CR 7, is closed for culvert replacement.  Detour: SR 49, SR 249, SR 2.  All work is weather permitting.

40. State Route 15: Culvert Replacement *CLOSURE BEGINS MONDAY*
Williams County:
 Effective Monday, July 13, through Friday, July 17, SR 15, between CR S and Kexon Drive, will be closed for culvert replacement.  Detour: US 20; SR 576; Territorial Road. Project complete: July.  All work is weather permitting.

41. State Route 107: Bridge Rehabilitation *CLOSURE BEGINS MONDAY*
Williams County (153-15):
 Effective Monday, July 13, through August, SR 107, between CR 8 and CR 9, will be closed for bridge rehabilitation.  Detour: SR 49; US 20; SR 576.  Project complete: September.  All work is weather permitting.   

42. State Route 65: Culvert Replacement
Henry County:
 Through Friday, July 10, SR 65, between CR F and CR G, will be closed for culvert replacement.  Detour: SR 18; SR 109; SR 281. All work is weather permitting.

43. State Route 65: Culvert Replacement *CLOSURE BEGINS MONDAY*
Henry County:
 Effective Monday, July 13, through August, SR 65, between CR K and CR N, will be closed for culvert replacement.  Detour: US 6; SR 109; SR 281. All work is weather permitting.  

44. State Route 109: Damascus Bridge: Bridge Replacement
Henry County (1-15):
  Through October 2017, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work.  Work impacting traffic will be announced.  Project complete: October 2017.  All work is weather permitting.

45. State Route 281: Culvert Replacement
Henry County (179-15):
 Through August, SR 281, between CR 17 and CR 19 will be closed for culvert replacement.  Detour: SR 108; SR 18.  Additionally, CR 18 is closed one mile north and one mile south of SR 281.  Project complete: August.  All work is weather permitting. 

District Wide 

46. Various Routes: Guardrail & Electrical Maintenance

District Wide (1071-14 & 1076-14): Through December, intermittent lane restrictions are possible district wide for guardrail and electrical maintenance.  Project complete: December. All work is weather permitting.