1. Interstate 75: Widening
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14): Through 2016, southbound I-75 is reduced to two lanes from US 20 to I-475 Perrysburg. Through 2016, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg to CR 99 in Hancock County. Project complete: October 2017.
Through Friday, March 27, from 8pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg to SR 18 for pavement repair.
Project complete: October 2017. All work is weather permitting.
2. Interstate 75: Widening *MAJOR CLOSURES BEGINNING FRIDAY*
Lucas County (485-14, 536-14): Project to widen I-75 from I-475 in Toledo to I-280. Through July 2018, overnight from 10pm until 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for traffic shifts. Motorists are advised traffic pattern changes in this work zone.
WEEKEND INTERCHANGE RAMP CLOSURE
Effective Friday, March 27 at 10pm, through Monday, March 30, at 6am, the ramp from northbound I-280 to southbound I-75 will be closed for barrier wall installation. Detour: northbound I-75; Alexis Road (Exit 201).
The following ramps will be closed:
· Through Saturday morning March 28, overnight from 10pm until 5am, the ramp from southbound I-75 to southbound I-280 will be closed for bridge work. Detour: North Expressway Drive (Exit 207); South Expressway Drive.
· Effective Friday, March 27, at 10pm through June 2016, the ramp from Philips Avenue to northbound I-75 will be closed for traffic maintenance. Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.
· The ramp from North Cove Boulevard to westbound I-475 will be permanently closed. Detour: Central Avenue; Detroit Avenue; Phillips Avenue.
· The ramp from eastbound I-475/northbound I-75 to Jeep Parkway will be permanently closed. Detour: Philips Avenue (Exit 206); Detroit Avenue; Berdan Avenue.
· Through July 2016, the ramp from northbound I-75 to Jeep Parkway (Exit 205A). Detour: Berdan Avenue (Exit 205B); Detroit Avenue.
· Through July 2018, the ramp from Jeep Parkway to southbound I-75. Detour: Berdan Avenue.
· Through July 2018, the ramp from Willys Parkway to northbound I-75. Detour: Berdan Avenue; Detroit Avenue; Philips Avenue.
· Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A). Detour: Detroit Avenue (Exit 203B).
Local Streets:
Through June 2016, Jeep Parkway from Central Avenue to Berdan Avenue will be closed. Central Avenue; Detroit Avenue; Berdan Avenue.
Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway will be closed.
Project complete: July 2018. All work is weather permitting.
3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14): Through July, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes. Through April, Oakwood Avenue, between Wells Street and Grove Place, will be closed for bridge work. Seek alternate route. Through July 2016, the following ramps will be restricted or closed:
· The interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.
· The interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.
· The ramp from Detroit Avenue to southbound I-75 is closed. Detour: Monroe Street; Michigan Avenue; SR 25.
All work is weather permitting. Project complete: July 2016. All work is weather permitting.
4. Interstate 475/U.S. Route 23: Interchange Upgrade
Lucas County (184-14): Lane restrictions are possible at the interchange of I-475/US 23 from Central Avenue to N. Holland Sylvania Road. Through April, lane restrictions are possible on Blossman Road, between Moffet Road and Plainview Drive for bridge work. Traffic will be maintained by flaggers. Project complete: December. All work is weather permitting.
5. Interstate 475: Bridge Widening
Lucas County (251-13 & 235-14): Through July, the ramp from Airport Highway to southbound I-475 is closed for bridge repair. Detour: I-475; Central Avenue (Exit 13). Through May 2016, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salsibury Road/Dussel Drive. 11-foot lane width restrictions are in place on I-475, between Angola Road and Salsibury Road/Dussel Drive. Through June 2016, lane and shoulder restrictions are possible on the Ohio Turnpike (I-80/I-90) at the I-475 bridge. Through June, Manley Road at the Ohio Turnpike Bridge is closed. Project complete: June 2016. All work is weather permitting.
6. Interstate 475: Noise Wall Installation
Lucas County (314-14): Through June, shoulder restrictions are possible on I-475, from Corey Road to Woodley Road, for noise wall installation. Overnight lane restrictions on I-475 will be announced. Project complete: June. All work is weather permitting.
7. Interstate 475: Bridge Deck Replacement
Lucas County (480-14): Through August, overnight from 9pm until 6am, single lane restrictions are possible on I-475 at Bancroft Street for bridge replacement. Through August, expect shoulder restrictions on I-475 at Bancroft Street for bridge repair. Though July, Bancroft Street at I-475 is closed for bridge replacement. Detour: Holland-Sylvania Road; Dorr Street; McCord Road. Project complete: August. All work is weather permitting.
8. State Route 2: Anthony Wayne Bridge Project *UPDATE*
Lucas County (58-13): Through November, the Anthony Wayne Bridge is closed to vehicular and pedestrian traffic. Detour: Oak Street; Fassett Street; Miami Street; I-75; Anthony Wayne Trail (Exit 201B); Monroe Street; Summit Street. Effective Monday, April 6, through June, Miami Street between Nevada Street and Greenwood Avenue, will be closed for bridge work. Detour: Fassett Street; Oak street. Effective Monday, March 30, through Friday, April, 3, Morris Street at the Anthony Wayne bridge will be closed for bridge deck removal. Detour: Ottawa Street; Broadway Street. Additionally, at this time, Utah Street at the Anthony Wayne bridge will be closed for bridge deck removal. Detour: Nevada Street; Yondota Street; Greenwood Avenue. Project complete: December. All work is weather permitting.
9. McCord Road: Underpass Construction
Lucas County (236-14): Through April, McCord Road, between North Mall Drive/Hall Street and Spectrum Drive, is reduced to one lane for traffic maintenance. Project complete: November 2016. All work is weather permitting.
10. U.S. Route 20: Holland Sylvania Road & Reynolds Road Intersection Improvements
Lucas County (145-14 & 252-14): Through June, lane restrictions are possible on Central Avenue from Fairbanks Avenue to Reynolds Road for median installation. Additionally, through June, expect lane restrictions on Holland-Sylvania Road, between Huntingfield Boulevard to Bonsels Parkway for median installation. Through June, intermittent lane restrictions are possible at the intersection of Central Avenue and Reynolds Road for safety improvements. Project complete: July. All work is weather permitting
11. Various Routes: Bridge Painting *NEW PROJECT*
Lucas County (8027-14): Effective Friday, March 27 through April, the right turn lane from southbound Summit Street (SR 51/65) to Oliver Street will be restricted for bridge painting. Suggested alternate route: Clayton Street. Work on Miami Street (SR 65) and on US 24 near Fallen Timbers will be announced. All work is weather permitting.
12. U.S. Route 6: Pavement Reconstruction
Wood County (170-14): Through Friday, March 27, additional lane restrictions are possible for pavement work. Traffic will be maintained by flaggers. Through October, US 6, between SR 25 and Dunbridge road, is reduced to one lane in each direction. Lane widths are restricted to 11ft in this work zone. Through October, the following ramps are closed for pavement reconstruction:
· The ramp from southbound I-75 to eastbound US 6. Detour: westbound US 6; SR 25.
· The ramp from northbound I-75 to westbound US 6. Detour: eastbound US 6; Dunbridge Road; Wooster Street (SR 105); southbound I-75.
Work complete: October. All work is weather permitting.
13. State Route 281: Bridge Replacement
Wood County (442-14): Through May, SR 281, between SR 25 and Solether Road, is closed for bridge replacement. Detour: SR 25; US 6; SR 199. Project complete: June. All work is weather permitting.
14. Gypsy Lane Road: Bridge Repair
Wood County (1093-14): Through July, Gypsy Lane Road over I-75 is reduced to one lane for bridge repair. Traffic is maintained by automated signal. Project complete: July. All work is weather permitting.
Ottawa/Sandusky/Seneca Counties
15. State Route 2: Mine Remediation
Ottawa County (27-13): Through May, SR 2 between SR 163 and SR 53 is reduced to one lane in each direction for mine remediation. Additionally, at this time, the ramp from southbound SR 53 to westbound SR 2 is closed. Detour: SR 53; SR 163. Project complete: May 2016. All work is weather permitting.
16. State Route 53: Safety Improvement Project *NEW PROJECT*
Ottawa County (468-14): Through May, intermittent single lane restrictions are possible on SR 53 between Wilcox Road and S. Wonnell Road for safety improvements. Project complete: June. All work is weather permitting.
17. U.S. Route 6: Bridge Repair
Sandusky (49-15): Effective Monday, April 13, through May, US 6, between CR 294 and TR 298, is closed for bridge repair. Detour: eastbound US 6; SR 269; SR 100; SR412; SR 510. westbound US 6; SR 269; SR 100; US 20. All work is weather permitting.
18. State Route 12: Bridge Rehabilitation
Sandusky and Seneca Counties (433-14): Through June, SR 12 over Wolf Creek between Seneca County Line Road and Sullivan Street in Bettsville will be closed for bridge rehabilitation. Detour: SR 635; US 6; SR 53. Additional restrictions will be announced. Project complete: July. All work is weather permitted.
19. State Route 412: Culvert Repair
Sandusky County (324-14): Through June, SR 412 between US 20 and SR 510 is closed for culvert repair. Detours: US 20; SR 510. Additional restrictions will be announced. Project complete: July. All work is weather permitted.
20. State Route 67: Bridge Repair
Seneca County (21-15): Effective Wednesday, April 1, through May, SR 67 between South Township Road 17 and East Township Road 42, south of Melmore, will be closed for bridge repair. Detour: SR 231; US 224; SR 100. Project complete May. All work is weather permitted.
Williams/Fulton/Henry Counties
21. State Route 281: Culvert Replacement
Henry County (442-14): Through June, SR 281, between CR 10 and SR 109, is closed for culvert replacement. Detour: SR 108; SR 18; SR 109. All work is weather permitting.
22. County Road 424: Stone Arch Replacement
Henry County (607-12): Through April, CR 424, between SR 109 and TR 6C, is closed for stone arch repair. Detour: SR 295; US 24; SR 109. Project complete: April. All work is weather permitting.
District Wide
23. Various Routes: Guardrail & Electrical Maintenance
District Wide (1071-14 & 1076-14): Through December, intermittent lane restrictions are possible district wide for guardrail and electrical maintenance. Project complete: December. All work is weather permitting.