North Baltimore, Ohio

April 18, 2024 11:36 am

Need A Chiropractor
TOP update from image Dec 2023
The District Update – Water Shed
OB You’re Expecting
June 2023 Left Rail
Ol’ Jenny
Fiber Locator
Logo & Info Aug 2023
Sept. 2023
Size Update
Logo
Temporary
Sept. 2023
Resize

Wood County Engineer’s Office Announces Bridge Replacement Projects

There will be a number of bridge replacement projects taking place in Wood County during the rest of this year.  Listed below are the bridges that will be closed for construction.  If an anticipated closure date is know, it has been included.  Otherwise, as the schedule gets closer, an update will be provided.  All the bridges listed below may not be in your area.  Bridge projects 1-7 are ran by ODOT and are part of their Bridge Partnership Program.  The remainder are managed by our office.

(Projects 5, 6,7 on this list are closest to our area of Wood County)

 

1.      Lime City over Grassy Creek – City of Rossford

·        Located south of Schreier Road

·        Start Date = July 18, 2016

·        Completion Date = September 6, 2016

2.      Collins Road over Henry Ditch – Village of Millbury/Lake Township

·        Located between Millbury and Bradner Road

·        Start Date = September 7, 2016

·        Completion Date = November 3, 2016

3.      Lemoyne Road over Toussaint Creek = Troy Township

·        Located between Garling and Gilbert Road

·        Start Date = October 13, 2016

·        Completion Date = November 15, 2016

4.      Dunbridge Road over Toussaint Creek = Center Township

·        Located between Simmons and Nelson Road

·        Start Date = September 12, 2016

·        Completion Date = October 12, 2016

5.      Liberty Hi Road over Middle Branch Portage River – Liberty Township

·        Located between SR 281 and Bays Road

·        Start Date = July 25, 2016

6.      Liberty Hi Road over North Branch Portage River – Liberty Township

·        Located between Mermill and Greensburg Pike Road

·        Start Date = August 1, 2016

7.      Henry Wood County Line over Brush Creek – Jackson Township

·        Located between Oil Center and Hammansburg Road

·        Start Date = July 18, 2016

8.      South River Road over Baker Ditch – Freedom Township

·        Located east of Wayne Road

·        45 day road closure

9.      Cygnet Road over South Branch Portage River – Perry Township

·        Located east of Emerson Road

10.   Emerson Road over Ditch 1756 – Perry/Bloom Townships

·        Located north of Cygnet Road

11.   Kramer Road over North Branch Portage River – Center/Portage Townships

·        Located between Shinew and County Home Road

 

 

Resize
Size Update
Sept. 2023
Sept. 2023
Logo & Info Aug 2023
June 2023 Left Rail
Temporary
Breast Cancer Treatment Rail Ad
Fiber Locator
OB You’re Expecting
Logo
Briar Hill Health Update
Ol’ Jenny

One Response

  1. Need to finish the wone they started next to interstate if they wasn`t going to finish it why did they tear it out oh yea the one on Broadway needs redone for the kids saftey need a bike trail too

Leave a Reply

Your email address will not be published. Required fields are marked *

NBX powered by PANDA Technologies
NBLS Website