BOWLING GREEN, Ohio – The Northwestern Water and Sewer District (The District) delivers water and sewer services to over 20,000 customer accounts in Wood, Henry, Sandusky, and Hancock counties. Although many of our projects are underground, our utility work can impact water and sewer service and roads throughout our area. Updates are highlighted in bold and underlined. All work is weather permitting.
Reminder: The District office will be closed, Thursday, November 27th and Friday, November 28th, in observance of the Thanksgiving Holiday. Call 419-354-9090 for water and sewer emergencies in your county.
McComb: Waterline Installation
Through March, lane and shoulder restrictions are possible on E. Main Street, east of Park Drive and at the intersection of Park Drive and Main Street for waterline installation. Traffic will be maintained by flaggers/temporary traffic signals. Project investment: $143,000. Project complete: March.
Through March, lane and shoulder restrictions are possible on E. Main Street, east of Park Drive and at the intersection of Park Drive and Main Street for waterline installation. Traffic will be maintained by flaggers/temporary traffic signals. Project investment: $143,000. Project complete: March.
Middleton and Center Township: SR 582/Dunbridge Water and Sewer Project
Through December intermittent lane and shoulder restrictions are possible along Dunbridge Road near SR 582 and on Mercer Road just south of SR 582 for restoration work. Project investment: $13.1 million. Project complete: December.
Northwood: Curtice Road Pump Station Replacement
Through December, the intersection of Bihl Avenue and Olde Curtice Road may be closed for pump station replacement work. Local access will be maintained. Project investment: $370,000. Project complete: December.
Northwood, Rossford, and Lake Township: Waterline Replacement Project *UPDATE*
Through December, lane and shoulder restrictions are possible on Glenwood Road from SR 795 to Buck Road for service line connections and waterline work. Traffic will be maintained by flaggers. Additional work in Northwood, Lake Township, and Rossford will be announced. Project investment: $5.6 million. Project complete: January.
Through December intermittent lane and shoulder restrictions are possible along Dunbridge Road near SR 582 and on Mercer Road just south of SR 582 for restoration work. Project investment: $13.1 million. Project complete: December.
Northwood: Curtice Road Pump Station Replacement
Through December, the intersection of Bihl Avenue and Olde Curtice Road may be closed for pump station replacement work. Local access will be maintained. Project investment: $370,000. Project complete: December.
Northwood, Rossford, and Lake Township: Waterline Replacement Project *UPDATE*
Through December, lane and shoulder restrictions are possible on Glenwood Road from SR 795 to Buck Road for service line connections and waterline work. Traffic will be maintained by flaggers. Additional work in Northwood, Lake Township, and Rossford will be announced. Project investment: $5.6 million. Project complete: January.
Perrysburg Township: Belmont Waterline Project *NEW PROECT*
Monday, December 1, through April, lane restrictions and road closures are possible for waterline replacement on the following roadways.
Monday, December 1, through April, lane restrictions and road closures are possible for waterline replacement on the following roadways.
- Simmons Road: from Mandell Road (south) to Mandell Road (north).
- Mandell Road: from Simmons Road to Belmont Lake Road
- Belmont Lake Road: from Mandell Road to Wethersfield Road
- Gleneagles Road: areas north of Ford Road
- Carnoustie Road and Carnoustie Court: west of Bates Road
Access to local traffic will be maintained. Project investment: $1.3 million. Project complete: July.
District Hydrant Flushing *UPDATE*
Crews have completed all hydrant flushing throughout our service area.
Crews have completed all hydrant flushing throughout our service area.